HomeMy WebLinkAbout2022-03-16FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Wednesday 3/16/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- We are backfilling the curbs
- Plugs are being removed from the Sanitary lift station
- Curbs are being backfilled along the entire eastern side of
the job in preparation for the fence
- We formed the small pad for the electric gate motor (We are
placing concrete tomorrow)
- Fencing from around the chemical manholes was removed.
and 2x4 were placed under the lids so the concrete will
continue to dry out.
- In Building 16 we are adding the louvers
- The 18" gasket at the declor pipe was not sitting right and
had to be adjusted.
2 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- The turbidity tanks are being moved
- Modifications are being made to the 14" valve
3 Daniel Ford No 60-PRODUCT WATER AREA - We are bolting up the 10" blind in this area.
- Anchoring of supports continues
4 Daniel Ford No 50-RO/UV BUILDING - We fabricated and installed PVC in this building
- Fabrication and install of the supports for the 12" line
- We are installing the louvers in the north wall.
- supports are being installed in this building.
- Holes are being cut in the east wall for the chemical lines.
5 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- Pipe supports were fabricated and delivered to this area
- On the NW corner we built some form work for a concrete
slab for a removable staircase.
6 Daniel Ford No 95-OPERATIONS
BUILDING
- We dug the hole for the flag pole and formed everything up.
We are ready to place concrete here tomorrow at noon
- The drain under the sidewalk near the flag pole has been
installed
FBV Morro Bay Joint Venture Page 1 of 9 Printed on 1/24/2023 at 10:11 AM PST
NOTES LOG
No.Created By Issue?Location Comments
7 Daniel Ford No 12-SITE OVERALL - YARD
PIPING
- We removed all plugs from the Sanitary lift station
8 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- We formed up a small slab on the NW corner of the the
building so they can bring a stair tower over to use the davit
crane.
9 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
- We are anchoring down the conveyor belt
MANPOWER LOG 30 Workers | 239.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 ELECTRICRAFT, INC.4 8.0 32.0
Notes:Created By: Rick Howland
2 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Esteban zamudio
Charlie Gonzales
Angel Diaz
Norman Gularte
Daniel Waddle
Manny Hernandez
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Alex Rios lopez
Teddy Maldanado
Javier Trevino
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
FBV Morro Bay Joint Venture Page 2 of 9 Printed on 1/24/2023 at 10:11 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Rick Jenne
Orlando Cortez
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Micha Pixley
Enrique Padilla
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Cement Mason
Daniel Sheslingoff
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Foreman
Phil Lacey
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 9 Printed on 1/24/2023 at 10:11 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
12 Allied Steel Co., Inc.3 6.0 18.0 30-TREATMENT
AREA
Notes:Sludge Tank Stair
Created By: Monica Weiss
13 Parada Painting Inc.2 10.0 20.0 60-PRODUCT
WATER AREA>65-
Product Water -
Disinfection
System (includes
dechlor station)
Notes:Created By: Monica Weiss
30 239.0
Manpower Log's Attachments:
1. ELECTRICRAFT, INC.
3-16-2022 Daily Report.xls
12. Allied Steel Co., Inc.
2022.03.16 Allied DFR.pdf
FBV Morro Bay Joint Venture Page 4 of 9 Printed on 1/24/2023 at 10:11 AM PST
13. Parada Painting Inc.
2022.03.16 Parada DFR.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 AHERN RENTAL 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
7 AHERN RENTAL 8.0 No 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
8 United Rental 8.0 No 11:25AM 00-GENERAL
Notes:loader
FBV Morro Bay Joint Venture Page 5 of 9 Printed on 1/24/2023 at 10:11 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
Created By: Daniel Ford
9 United Rental 8.0 No 11:25AM 00-GENERAL
Notes:Bull dozer
Created By: Daniel Ford
10 United Rental No 10:15AM 00-GENERAL
Notes:Jumping Jack
Created By: Daniel Ford
11 United Rental No 10:15AM
Notes:Water truck
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 11:00AM AHERN RENTALS - SANTA
MARIA
24689758 Boom Lift 60'
Comments:Created By: Monica Weiss
2 11:00AM AHERN RENTALS - SANTA
MARIA
24689759 Snorkel Scissorlift
Comments:Created By: Monica Weiss
3 11:00AM Ferguson Enterprises, LLC 471-226 Speedi-basin
Comments:Created By: Monica Weiss
4 11:00AM Ferguson Enterprises, LLC 471-247
Comments:Created By: Monica Weiss
5 11:00AM Harrington Industrial Plastics
LLC
MR141 Inj Q
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
FBV Morro Bay Joint Venture Page 6 of 9 Printed on 1/24/2023 at 10:11 AM PST
1.
2022.03.16 Ahern boom 9768.pdf
2.
2022.03.16 Ahern Scissorlift 9759.pdf
3.
2022.03.16 Ferguson 471-226 Speedibasin.pdf
FBV Morro Bay Joint Venture Page 7 of 9 Printed on 1/24/2023 at 10:11 AM PST
4.
2022.03.16 Ferguson 471-241.pdf
5.
2022.03.16 Harrington MR 141 InjQ.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
48°F 60°F 52°F 0.00 in.0.00 in.0.00 in.67%87%100%49°F 3.3 mph 7 mph 10 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Cloudy
50°F
Partly Cloudy
50°F
Clear
55°F
Clear
60°F
Clear
57°F
Clear
51°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 07:25:00 AM No
FBV Morro Bay Joint Venture Page 8 of 9 Printed on 1/24/2023 at 10:11 AM PST
By Date Copies To
FBV Morro Bay Joint Venture Page 9 of 9 Printed on 1/24/2023 at 10:11 AM PST