HomeMy WebLinkAbout2022-03-17FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Thursday 3/17/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- We are backfilling the curbs
- Wattles are being removed from the road
- Curbs are being backfilled along the entire eastern side of
the job in preparation for the fence
- Concrete was placed in the pad for the electrical gate motor,
the staircase pad at the NW corner of the BNR tank, and the
flagpole base.
- Jobsite Clean up
- Ricardo, Jonathan,Manny, Enrique,Phillip, And Trevor took a
shoring class off site.
2 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- Pancakes were being removed from the 12, and 18 inch lines
on the south side of the MBR slab.
-
3 Daniel Ford No 50-RO/UV BUILDING - We fabricated and installed PVC in this building
- We are installing the louvers in the north wall.
- FRP supports are being installed in this building for the
chemical lines.
- Holes are being cut in the east wall for the chemical lines.
4 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- We are installing the BV Air in this area.
- The ariel life showed up on site and we ran it out to make it
would reach everywhere we needed.
- We brought up all the pipe supports and valves to this area.
5 Daniel Ford No 95-OPERATIONS
BUILDING
- We dug the hole for the flag pole and formed everything up.
We are ready to place concrete here tomorrow at noon
- The drain under the sidewalk near the flag pole has been
installed
FBV Morro Bay Joint Venture Page 1 of 8 Printed on 1/24/2023 at 10:12 AM PST
MANPOWER LOG 30 Workers | 233.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 ELECTRICRAFT, INC.4 8.0 32.0
Notes:Created By: Rick Howland
2 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Esteban zamudio
Charlie Gonzales
Angel Diaz
Norman Gularte
Daniel Waddle
Manny Hernandez
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Alex Rios lopez
Teddy Maldanado
Javier Trevino
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Rick Jenne
Orlando Cortez
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Micha Pixley
Enrique Padilla
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
FBV Morro Bay Joint Venture Page 2 of 8 Printed on 1/24/2023 at 10:12 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Cement Mason
Daniel Sheslingoff
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Foreman
Phil Lacey
Created By: Daniel Ford
12 Allied Steel Co., Inc.3 4.0 12.0
Notes:GRATING
Created By: Monica Weiss
13 Parada Painting Inc.2 10.0 20.0 20-HEADWORKS
AREA
Notes:Created By: Monica Weiss
30 233.0
Manpower Log's Attachments:
1. ELECTRICRAFT, INC.
3-17-2022 Daily Report.xls
FBV Morro Bay Joint Venture Page 3 of 8 Printed on 1/24/2023 at 10:12 AM PST
12. Allied Steel Co., Inc.
2022.03.17 Allied DFR.pdf
13. Parada Painting Inc.
2022.03.17 Parada DFR.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 8 Printed on 1/24/2023 at 10:12 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 AHERN RENTAL 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
7 AHERN RENTAL 8.0 No 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
8 United Rental 8.0 No 11:25AM 00-GENERAL
Notes:loader
Created By: Daniel Ford
9 United Rental 8.0 No 11:25AM 00-GENERAL
Notes:Bull dozer
Created By: Daniel Ford
10 United Rental No 10:15AM 00-GENERAL
Notes:Jumping Jack
Created By: Daniel Ford
11 United Rental No 10:15AM
Notes:Water truck
Created By: Daniel Ford
12 AHERN RENTAL 8.0 No 02:10PM
Notes:35' Ariel lift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 11:10AM Allied Steel Co., Inc.Angle
Comments:Created By: Monica Weiss
2 11:10AM CalPortland 1739830 Eq Pad Flagpole
Comments:Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 5 of 8 Printed on 1/24/2023 at 10:12 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
3 11:10AM Ferguson Enterprises, LLC 471-235
Comments:Created By: Monica Weiss
4 11:10AM Miner's Ace Hardware 732929 A50
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.03.17 Allied Steel Angle.pdf
2.
2022.03.17 Calportland 1739830 Eqpad Flagpole.pdf
FBV Morro Bay Joint Venture Page 6 of 8 Printed on 1/24/2023 at 10:12 AM PST
3.
2022.03.17 Ferguson 471-235.pdf
4.
2022.03.17 Miners 732929 A50.pdf 2022.03.17 Ferguson 471-235.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
48°F 61°F 53°F 0.00 in.0.00 in.0.00 in.67%82%99%48°F 3.6 mph 7 mph 10 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
50°F
Clear
50°F
Cloudy
57°F
Cloudy
62°F
Clear
58°F
Cloudy
51°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 07:20:00 AM No
FBV Morro Bay Joint Venture Page 7 of 8 Printed on 1/24/2023 at 10:12 AM PST
By Date Copies To
FBV Morro Bay Joint Venture Page 8 of 8 Printed on 1/24/2023 at 10:12 AM PST