HomeMy WebLinkAbout2022-03-24FBV Morro Bay Joint Venture 2999 Oak Rd. #490 Walnut Creek , California 94597 Project: 471 - Morro Bay Water Reclamation Facility  Morro Bay , California 93442 Daily Log: Thursday 3/24/2022    NOTES LOG    No.Created By Issue?Location Comments   1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed. - The 24" PVC declor pipe is being modified - The patch for low spot for the V ditch north of the head works. - We spent 16 hours (Trevor and Johnny) excavating for the eastern fence around electrical conduits - We spent 16 hours (Kyle and Estevan) backfilling from the electrical reroute (eastern fence) and managing the spoils 2 Daniel Ford No 50-RO/UV BUILDING - Fabrication and installation continue - FRP supports are being installed in this building for the chemical lines. 3 Daniel Ford No 96-MAINTENANCE BUILDING - We are installing the fire extinguisher in this building. - The sinks are being installed in the lab 4 Daniel Ford No 60-PRODUCT WATER AREA - We removed a dismantling joint for pump 3 and are investigating the " noise" that its making. - pumps were adjusted and connected. - Pipe Supports continued to be grouted in - We are adjusting the check valves and tightening up a few leaking spots. 5 Daniel Ford No 30-TREATMENT AREA>31- Treatment Area - BNR Basins - We are working on the pipe supports and welding the Stainless steel plates for this area. - Fabrication and grinding continues for the support plates 6 Daniel Ford No 70-RESIDUALS AREA>73- Residuals Area - SAFE Filter System - We are bolting up the 4" SHT - The Safe filter has been filled and the start up work continues 7 Daniel Ford No 20-HEADWORKS AREA - The start up tech for the fine screens was here and completed his work yesterday. - Kusters is here troubleshooting problems, taking care of punch list items, working on start up procedures, and getting   FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 10:14 AM PST          NOTES LOG    No.Created By Issue?Location Comments   together all spare parts. - We filled up the Safe filter box. 8 Daniel Ford No 70-RESIDUALS AREA>71- Residuals Area - Sludge Holding Tanks & SAFE Settle Tank - We patched all remaining holes in the SAFE settle tank and the SHT - All items have been removed and the SAFE settle tank is being filled with clean water - The penetrations in the western wall are being SIKA flexed on the wet side and have already had the link seals and sleeves installed. - The temporary air supports area being removed and the permanent ones are being installed. - We are filing the SAFE filter tank with water.   MANPOWER LOG 23 Workers  |   176.0 Man Hours No.Contact/Company Workers # Hours Man Hours Location     1 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL     Notes:JOURNEYMAN LABORERS Esteban zamudio Charlie Gonzales Angel Diaz Norman Gularte Daniel Waddle Manny Hernandez Created By:  Daniel Ford    2 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL     Notes:LABORER APPRENTICE Jonathan Torres Teddy Maldonado Javier Trevino Created By:  Daniel Ford    3 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL     Notes:JOURNEYMAN CARPENTERS Coy Brite Rick Jenne     FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 10:14 AM PST        No.Contact/Company Workers # Hours Man Hours Location     Orlando Cortez Created By:  Daniel Ford  4 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL     Notes:CARPENTER APPRENTICE Micha Pixley Enrique Padila Rafael Alvarado Created By:  Daniel Ford    5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL     Notes:Certified Welder Pipefitter Rick Dayton Created By:  Daniel Ford    6 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL     Notes:Operator Trevor Hernandez Kyle Brooking Created By:  Daniel Ford    7 J.R. Filanc Construction Company, Inc.1 8.0 8.0     Notes:Cement Mason Daniel Sheslingoff Created By:  Daniel Ford    8 J.R. Filanc Construction Company, Inc.1 0.0 0.0 00-GENERAL     Notes:Labor Foreman Ricardo Belmontes Created By:  Daniel Ford    9 ELECTRICRAFT, INC.4 8.0 32.0     Notes:Created By:  Rick Howland      23  176.0    Manpower Log's Attachments:  9.  ELECTRICRAFT, INC.    3-24-2022 Daily Report.xls     FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 10:14 AM PST          EQUIPMENT LOG No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location   1 United Rental 8.0 No   12:20PM  00-GENERAL  Notes:Scissor lift Created By: Daniel Ford   2 AHERN RENTAL 8.0 No   05:40AM    Notes:45' ariel lift Created By: Daniel Ford   3 AHERN RENTAL 8.0 No   02:00PM  00-GENERAL  Notes:Telescoping Forklift Created By: Daniel Ford   4 AHERN RENTAL 8.0 No   11:25AM  00-GENERAL  Notes:Skid steer Created By: Daniel Ford   5 United Rental 8.0 No   11:25AM  00-GENERAL  Notes:loader Created By: Daniel Ford   6 United Rental No   10:15AM  00-GENERAL  Notes:Jumping Jack Created By: Daniel Ford   7 United Rental No   10:15AM    Notes:Water truck Created By: Daniel Ford   8 AHERN RENTAL 8.0 No   02:10PM    Notes:35' Ariel lift Created By: Daniel Ford   9 No   05:30AM    Notes:Created By: Daniel Ford     DELIVERY LOG No.Time Delivery From Tracking Number Contents   1 02:35PM   Shore-Tek Inc.Trench Plate    Comments:Created By: Monica Weiss   FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 10:14 AM PST          DELIVERY LOG No.Time Delivery From Tracking Number Contents   2 02:35PM   Miner's Ace Hardware 733563    Comments:Created By: Monica Weiss 3 02:35PM   kusters ACID    Comments:Created By: Monica Weiss 4 02:35PM   Airgas 6009 Argon Gloves Wheels    Comments:Created By: Monica Weiss Delivery Log's Attachments: 1.  2022.03.24 Shoretek Trench Plate.pdf 2.  2022.03.24 Miners 733563.pdf   FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 10:14 AM PST        3.  2022.03.24 Kusters Zima Acid.pdf 4.  2022.03.24 Airgas 6009 Argon Gloves wheels.pdf   WEATHER REPORT Temperature Precipitation Since Humidity Windspeed Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust 45°F 55°F 50°F 0.00 in.0.00 in.0.00 in.86%93%99%48°F 3.3 mph 5 mph 9 mph   DAILY SNAPSHOT 06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM Clear   45°F Clear   49°F Clear   56°F Clear   54°F Clear   52°F Clear   50°F   OBSERVED WEATHER CONDITIONS No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea   1 05:45:00 AM No     FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 10:14 AM PST            By  Date  Copies To   FBV Morro Bay Joint Venture Page 7 of 7 Printed on 1/24/2023 at 10:14 AM PST