HomeMy WebLinkAbout2022-03-31FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Thursday 3/31/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - We were working on the landscape sub grade
- Layout, excavation, for the trench behind the chem building
- Excavation and pipe install for the 2" pipe for pond 1 man
hole pump.
- The 24" PVC declor pipe is being modified
- The V ditches were being cleaned out and the dirt around
them is being leveled out for the landscapers
- We put fencing up around the open chem vault man holes
2 Daniel Ford No 50-RO/UV BUILDING - Fabrication and installation continue
- FRP supports are being installed in this building for the
chemical lines.
- We are setting up sidewalks outside on the north and south
entrance
- Forming pipe supports pads
- We epoxied in anchors for the 3 chemical tanks and the UV
system
3 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- We are working on the pipe supports and welding the
Stainless steel plates for this area.
- Fabrication, and grinding continues for the support plates
- Both tanks are being cleaned and filled with water to a inch
above the diffusers
4 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
- We patched all remaining holes in the SAFE settle tank and
the SHT
- All items have been removed and the SAFE settle tank is
being filled with clean water
- We are filing the SAFE filter tank with water.
- Both SHT's are cleaned and ready to be filled with water to
test the air diffusers.
5 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- Angle is being cut and fabricated for the cassette tank
- Blinds are being installed form the scum tank
- angel is being cut for the cassette tank supports
FBV Morro Bay Joint Venture Page 1 of 5 Printed on 1/24/2023 at 10:16 AM PST
NOTES LOG
No.Created By Issue?Location Comments
- Pipe supports pads
- the stainless steel air lines are being pickled
6 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
- Ball valves are being installed for the drains
7 Daniel Ford No 60-PRODUCT WATER AREA - We are working on the grout pads and some pipe supports.
8 Daniel Ford No 70-RESIDUALS AREA>73-
Residuals Area - SAFE Filter
System
- Forming pipe supports pads
9 Daniel Ford No 90-CHEMICAL FACILITY - Fabricate and install RO supports in the chem area
- Layout in this area
- Eye wash stations are being installed
- Pipe supports are being worked on in this building
- We are installing the pipe in tis area.
10 Daniel Ford No 96-MAINTENANCE
BUILDING
- We laid down the epoxy floor in the lab of the maintenance
building
11 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
- The conveyor is being installed
MANPOWER LOG 25 Workers | 192.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 ELECTRICRAFT, INC.6 8.0 48.0
Notes:Created By: Rick Howland
2 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Charlie Gonzales
Angel Diaz
Norman Gularte
Daniel Waddle
Manny Hernandez
FBV Morro Bay Joint Venture Page 2 of 5 Printed on 1/24/2023 at 10:16 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Javier Trevino
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Rick Jenne
Orlando Cortez
Andrew Seleva
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Micha Pixley
Enrique Padilla
Rafael Alvarado
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Cement Mason
Daniel Sheslingoff
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 0.0 0.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
FBV Morro Bay Joint Venture Page 3 of 5 Printed on 1/24/2023 at 10:16 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Foreman
Phil Lacey
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Cement Masons
Adolfo Campoverde
Created By: Daniel Ford
25 192.0
Manpower Log's Attachments:
1. ELECTRICRAFT, INC.
3-31-2022 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 No 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
5 United Rental 8.0 No 11:25AM 00-GENERAL
Notes:loader
Created By: Daniel Ford
6 United Rental No 10:15AM 00-GENERAL
Notes:Jumping Jack
FBV Morro Bay Joint Venture Page 4 of 5 Printed on 1/24/2023 at 10:16 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
Created By: Daniel Ford
7 United Rental No 10:15AM
Notes:Water truck
Created By: Daniel Ford
8 AHERN RENTAL 8.0 No 02:10PM
Notes:35' Ariel lift
Created By: Daniel Ford
9 No 05:30AM
Notes:Created By: Daniel Ford
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
45°F 54°F 51°F 0.00 in.0.00 in.0.00 in.75%86%95%47°F 7.1 mph 11 mph 17 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Partly Cloudy
46°F
Partly Cloudy
50°F
Partly Cloudy
54°F
Clear
55°F
Clear
52°F
Partly Cloudy
53°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 06:00:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 5 of 5 Printed on 1/24/2023 at 10:16 AM PST