HomeMy WebLinkAbout2022-04-04FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Monday 4/4/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Watering hydroseed
- concrete pour all over the site (small pads, pipe supports and
pipe encasements.)
- clean up and throwing trash away
- cleaning concrete off of door and walls
- We fixed the drainage problem in one of the vaults.
- The painters are starting there coating process in the
chemical vaults
- We backfiled the area behind the product water tank
2 Daniel Ford No 50-RO/UV BUILDING - Fabrication and installation continue of PVC and CPVC pipes
- A small sidewalks was poured at the north and south
entrance of this building
- a small pad was placed in concrete where the chemical pipes
come into the building
3 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- We are working on the pipe supports and welding the
Stainless steel plates for this area.
- Fabrication, and grinding continues for the support plates
- We are setting and anchoring in the pipe supports
4 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- We cast a pad under the Mixed liquor line for asphalt and to
place a pipe support for the 2 20 in lines
- Pipe supports pads
- the stainless steel air lines are being pickled
5 Daniel Ford No 60-PRODUCT WATER AREA - We are working on the grout pads and some pipe supports.
6 Daniel Ford No 90-CHEMICAL FACILITY - Fabricate and install RO supports in the chem area
- Layout in this area
- Eye wash stations are being installed
- Pipe supports are being worked on in this building
- We encased a sleeve in the 3 inch water line where goes over
the conduit underground
FBV Morro Bay Joint Venture Page 1 of 10 Printed on 1/24/2023 at 10:33 AM PST
NOTES LOG
No.Created By Issue?Location Comments
7 Daniel Ford No 96-MAINTENANCE
BUILDING
- We laid down the epoxy floor in the lab of the maintenance
building
8 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
MANPOWER LOG 28 Workers | 220.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Charlie Gonzales
Angel Diaz
Norman Gularte
Daniel Waddle
Manny Hernandez
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Javier Trevino
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Rick Jenne
Orlando Cortez
Andrew Seleva
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 10 Printed on 1/24/2023 at 10:33 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
4 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Micha Pixley
Enrique Padilla
Rafael Alvarado
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.0 8.0 0.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Cement Mason
Daniel Sheslingoff
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 0.0 0.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Foreman
Phil Lacey
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Cement Masons
Adolfo Campoverde
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 10 Printed on 1/24/2023 at 10:33 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
12 ELECTRICRAFT, INC.6 8.0 48.0
Notes:Created By: Rick Howland
13 Parada Painting Inc.2 10.0 20.0 10-SITE
OVERALL
Notes:sandblasting Vaults
Created By: Monica Weiss
28 220.0
Manpower Log's Attachments:
12. ELECTRICRAFT, INC.
4-4-2022 Daily Report.xls
13. Parada Painting Inc.
0404 PARADA STA.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 10 Printed on 1/24/2023 at 10:33 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
4 AHERN RENTAL 8.0 No 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
5 United Rental 8.0 No 11:25AM 00-GENERAL
Notes:loader
Created By: Daniel Ford
6 United Rental No 10:15AM 00-GENERAL
Notes:Jumping Jack
Created By: Daniel Ford
7 United Rental No 10:15AM
Notes:Water truck
Created By: Daniel Ford
8 AHERN RENTAL 8.0 No 02:10PM
Notes:35' Ariel lift
Created By: Daniel Ford
9 No 05:30AM
Notes:Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 09:00AM CalPortland Sidewalk Pads
Comments:Created By: Monica Weiss
2 09:00AM Ferguson Enterprises, LLC 471-263.1
Comments:Created By: Monica Weiss
3 09:00AM Ferguson Enterprises, LLC 2in Pipe CPVC
Comments:Created By: Monica Weiss
4 09:00AM Ferguson Enterprises, LLC SS Strut
Comments:Created By: Monica Weiss
5 09:00AM Grainger 3in ARV
Comments:Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 5 of 10 Printed on 1/24/2023 at 10:33 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
6 09:00AM HARRINGTON INDUSTRIAL
PLASTICS LLC
Pump & Tubing for Inj Quills
Comments:Created By: Monica Weiss
7 09:00AM Miner's Ace Hardware 734362 Rebar
Comments:Created By: Monica Weiss
8 09:00AM PACIFIC COAST BOLT CORP 1096100 471-260
Comments:Created By: Monica Weiss
9 09:00AM PACIFIC COAST BOLT CORP Wedge Anchors
Comments:Created By: Monica Weiss
10 09:00AM PACIFIC COAST BOLT CORP All Thread 471-260
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.04.04 Calportland Sidewalk Pads.pdf
FBV Morro Bay Joint Venture Page 6 of 10 Printed on 1/24/2023 at 10:33 AM PST
2.
2022.04.04 Ferguson 471-263.1.pdf
3.
2022.04.04 Ferguson CPVC 2in Pipe.pdf
4.
2022.04.04 Ferguson SS Strut.pdf
FBV Morro Bay Joint Venture Page 7 of 10 Printed on 1/24/2023 at 10:33 AM PST
5.
2022.04.04 Grainger 3in Valves ARV.pdf
6.
2022.04.04 Harrington Pump &Tubing for Inj Q.pdf
7.
2022.04.04 Miners Rebar 734362.pdf
FBV Morro Bay Joint Venture Page 8 of 10 Printed on 1/24/2023 at 10:33 AM PST
8.
2022.04.04 Pac Coast Bolt 471-260 1096100.pdf
9.
2022.04.04 Pac Coast Bolt Wedge Anchors.pdf
10.
2022.04.04 Pacific Coast Bolt 471-260 All Thread.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
46°F 58°F 53°F 0.00 in.0.00 in.0.00 in.56%80%94%47°F 5.4 mph 10 mph 15 mph
FBV Morro Bay Joint Venture Page 9 of 10 Printed on 1/24/2023 at 10:33 AM PST
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
46°F
Clear
56°F
Clear
56°F
Clear
58°F
Clear
58°F
Clear
55°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 06:00:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 10 of 10 Printed on 1/24/2023 at 10:33 AM PST