Daily Log: Wednesday 4/6/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Watering hydroseed
- concrete pour all over the site (small pads, pipe supports and
pipe encasements.)
- We were working on the chem lines
- landscaping sub grade continues to be worked on
- The painters are starting there coating process in the
chemical vaults
- all pipes and handrail were wrapped in plastic so williams
concrete can come and do there concrete patching
- We fabricated a temporary pipe for the declore area so we
can continue with process testing
2 Daniel Ford No 50-RO/UV BUILDING - Fabrication and installation continue of PVC and CPVC pipes
- A small sidewalks was poured at the north and south
entrance of this building
- stripping the forms and cleaning up from the pours
yesterday
3 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- We are working on the pipe supports and welding the
Stainless steel plates for this area.
- Fabrication, and grinding continues for the support plates
- We are setting and anchoring in the pipe supports
4 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- stripping the forms and cleaning up from the pours
yesterday
- Pipe supports pads are being worked on and drilled and
anchored into place
- the stainless steel air lines are being pickled
- Blowers and the WAS/scum pumps are being tested on this
slab.
5 Daniel Ford No 60-PRODUCT WATER AREA - We are working on the grout pads and some pipe supports.
6 Daniel Ford No 90-CHEMICAL FACILITY - Fabricate and install RO supports in the chem area
- Layout in this area
FBV Morro Bay Joint Venture Page 1 of 9 Printed on 1/24/2023 at 10:34 AM PST
NOTES LOG
No.Created By Issue?Location Comments
- Eye wash stations are being installed
- Pipe supports are being worked on in this building
7 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
- Pipe supports are being worked on in this area
- Blowers and diffusers ares being tested in this area
MANPOWER LOG 28 Workers | 220.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Charlie Gonzales
Angel Diaz
Norman Gularte
Daniel Waddle
Manny Hernandez
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Javier Trevino
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Rick Jenne
Orlando Cortez
Andrew Seleva
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 9 Printed on 1/24/2023 at 10:34 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
4 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Micha Pixley
Enrique Padilla
Rafael Alvarado
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.0 8.0 0.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Cement Mason
Daniel Sheslingoff
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 0.0 0.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Foreman
Phil Lacey
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Cement Masons
Adolfo Campoverde
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 9 Printed on 1/24/2023 at 10:34 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
12 ELECTRICRAFT, INC.6 8.0 48.0
Notes:Created By: Rick Howland
13 Parada Painting Inc.2 10.0 20.0 90-CHEMICAL
FACILITY
Notes:Created By: Monica Weiss
28 220.0
Manpower Log's Attachments:
12. ELECTRICRAFT, INC.
4-6-2022 Daily Report.xls
13. Parada Painting Inc.
0406 PARADA STA.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 Yes 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 Yes 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 9 Printed on 1/24/2023 at 10:34 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
4 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
5 United Rental 8.0 Yes 11:25AM 00-GENERAL
Notes:loader
Created By: Daniel Ford
6 United Rental Yes 10:15AM
Notes:Water truck
Created By: Daniel Ford
7 AHERN RENTAL 8.0 Yes 02:10PM
Notes:35' Ariel lift
Created By: Daniel Ford
8 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 09:20AM Ferguson Enterprises, LLC 2in CPVC
Comments:Created By: Monica Weiss
2 09:20AM Ferguson Enterprises, LLC 6*4 bushings Damaged
Comments:Return has been requested
Created By: Monica Weiss
3 09:20AM Ferguson Enterprises, LLC 471-240 CPVC
Comments:Created By: Monica Weiss
4 09:20AM Ferguson Enterprises, LLC SCH 80 pipe
Comments:Created By: Monica Weiss
5 09:20AM Suez Water Technologies &
Solutions
Toe Nipple
Comments:Created By: Monica Weiss
6 09:20AM WERNER Harness
Comments:Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 5 of 9 Printed on 1/24/2023 at 10:34 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
7 09:20AM HD Supply White Cap 46662325 Knaack Springs welder gloves
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.04.06 Ferguson 2in CPVC Pipe.pdf
2.
2022.04.06 Ferguson 6x4 Bushing Damaged.pdf
FBV Morro Bay Joint Venture Page 6 of 9 Printed on 1/24/2023 at 10:34 AM PST
3.
2022.04.06 Ferguson 471-240 CPVC Fittings.pdf
4.
2022.04.06 Ferguson SCH80 Pipe.pdf
5.
2022.04.06 SUEZ Toe Nipple.pdf
FBV Morro Bay Joint Venture Page 7 of 9 Printed on 1/24/2023 at 10:34 AM PST
6.
2022.04.06 Werner Co .pdf
7.
2022.04.06 White Cap 46662325.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
60°F 86°F 72°F 0.00 in.0.00 in.0.00 in.19%28%42%37°F 8.2 mph 15 mph 25 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
61°F
Clear
69°F
Clear
78°F
Clear
87°F
Clear
85°F
Clear
78°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:45:00 AM No
FBV Morro Bay Joint Venture Page 8 of 9 Printed on 1/24/2023 at 10:34 AM PST
By Date Copies To
FBV Morro Bay Joint Venture Page 9 of 9 Printed on 1/24/2023 at 10:34 AM PST