HomeMy WebLinkAbout2022-04-08FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Friday 4/8/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Watering hydroseed
- we are cleaning the entrance area
- Manholes are being cleaned out.
- landscaping sub grade continues to be worked on
- The painters are starting there coating process in the
chemical vaults
- We had a plug in one of the man holes and we had to chip
out some slurry and clean out gravel to clear it
2 Daniel Ford No 50-RO/UV BUILDING - Fabrication and installation continue of PVC and CPVC pipes
- We are installing supports in this building.
3 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- We are setting and anchoring in the pipe supports
- Williams Concrete is sacking the southern wall of the BNR
tank.
4 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- Pipe supports pads are being worked on and drilled and
anchored into place
- All the diffuser blowers are up and running.
5 Daniel Ford No 60-PRODUCT WATER AREA - We are working on the grout pads and some pipe supports.
6 Daniel Ford No 90-CHEMICAL FACILITY - Fabricate and install RO supports in the chem area
- Piping continues to be installed in this area.
- Pipe supports are being worked on in this building
7 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
- Pipe supports are being worked on in this area
- Water is not draining from the northern tank, so we are
pumping it out to investigate the situation.
FBV Morro Bay Joint Venture Page 1 of 6 Printed on 1/24/2023 at 10:36 AM PST
MANPOWER LOG 25 Workers | 192.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 ELECTRICRAFT, INC.5 8.0 40.0
Notes:Created By: Rick Howland
2 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Charlie Gonzales
Angel Diaz
Norman Gularte
Daniel Waddle
Manny Hernandez
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Javier Trevino
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Rick Jenne
Orlando Cortez
Andrew Seleva
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Micha Pixley
Enrique Padilla
Rafael Alvarado
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 6 Printed on 1/24/2023 at 10:36 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
6 J.R. Filanc Construction Company, Inc.0 8.0 0.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Cement Mason
Daniel Sheslingoff
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 0.0 0.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Foreman
Phil Lacey
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Cement Masons
Adolfo Campoverde
Created By: Daniel Ford
12 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
25 192.0
Manpower Log's Attachments:
1. ELECTRICRAFT, INC.
4-8-2022 Daily Report.xls
FBV Morro Bay Joint Venture Page 3 of 6 Printed on 1/24/2023 at 10:36 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 Yes 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 Yes 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
5 United Rental 8.0 Yes 11:25AM 00-GENERAL
Notes:loader
Created By: Daniel Ford
6 United Rental Yes 10:15AM
Notes:Water truck
Created By: Daniel Ford
7 AHERN RENTAL 8.0 Yes 02:10PM
Notes:35' Ariel lift
Created By: Daniel Ford
8 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 09:50AM Allied Steel Co., Inc.Steel Galv ANgles
Comments:Created By: Monica Weiss
2 09:50AM Ferguson Enterprises, LLC 1.5 VSF
Comments:Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 4 of 6 Printed on 1/24/2023 at 10:36 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
3 09:50AM Allied Steel Co., Inc.Grating Pacific
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.04.08 Allied Steel Galv Angles.pdf
2.
2022.04.08 Ferguson 1.5 VSF.pdf
FBV Morro Bay Joint Venture Page 5 of 6 Printed on 1/24/2023 at 10:36 AM PST
3.
2022.04.08 Grating Pacific Allied.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
54°F 84°F 69°F 0.00 in.0.00 in.0.00 in.29%47%82%46°F 3.5 mph 5 mph 12 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
74°F
Clear
77°F
Clear
85°F
Clear
76°F
Clear
67°F
Cloudy
58°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 07:40:00 AM No
By Date Copies To