HomeMy WebLinkAbout2022-04-11FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Monday 4/11/2022
Daily Log Completed
The Daily Log was completed by Monica Weiss on Tue May 3, 2022 at 10:24amPDT.
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Watering hydroseed
- The top 2 sections of the Manhole near the Vacor pad were
removed and barricaded off so we can build a interior weir
wall inside.
- Manholes are being cleaned out.
- landscaping sub grade continues to be worked on
- General clean up around site
- We are filing tanks all over the job BNR,SHT, Product water
tank, outfall balance tank
2 Daniel Ford No 50-RO/UV BUILDING - Fabrication and installation continue of PVC and CPVC pipes
- We are installing supports in this building.
- We are installing the 2" pipe and a valve in this area.
- Air vac was installed in this area
- Chemical injection quills are being installed
3 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- We are setting and anchoring in the pipe supports
4 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- Pipe supports pads are being worked on and drilled and
anchored into place
- All the diffuser blowers are up and running. (SUEZ continues
with there testing)
- The chemical quills are being installed in the RO feed area
- Piping continues to be installed for the cassette tank
- We are setting up for the commission test at the cassette
tank.
5 Daniel Ford No 90-CHEMICAL FACILITY - Fabricate and install the 1 1/2 inch cs lines in this area
- Piping continues to be installed in this area.
- Pipe supports are being worked on in this building
FBV Morro Bay Joint Venture Page 1 of 9 Printed on 1/24/2023 at 10:37 AM PST
NOTES LOG
No.Created By Issue?Location Comments
6 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
- Pipe supports are being worked on in this area
- Water is not draining from the northern tank, so we are
pumping it out to investigate the situation.
7 Daniel Ford No 20-HEADWORKS AREA>24-
Headworks Area - Vactor
Washdown
- We are digging around the 6 inch drain line in the bottom of
the vacor pad.
8 Daniel Ford No 60-PRODUCT WATER AREA - Supports are being installed for the outfall area.
- Air vac was installed in this area
9 Daniel Ford No 95-OPERATIONS
BUILDING
- We are taking care of concrete punch list items in this
building (4,25,38,41,52 and 57)
- We took care of punch list items for 1,2,5,18,26,27, 45, and 47
MANPOWER LOG 27 Workers | 212.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Charlie Gonzales
Angel Diaz
Norman Gularte
Daniel Waddle
Manny Hernandez
Esteban Zamudio
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Javier Trevino
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
FBV Morro Bay Joint Venture Page 2 of 9 Printed on 1/24/2023 at 10:37 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Coy is brite
Orlando Cortez
Andrew Seleva
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Micha Pixley
Enrique Padilla
Rafael Alvarado
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.0 8.0 0.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Cement Mason
Daniel Sheslingoff
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 0.0 0.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Foreman
Phil Lacey
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Cement Masons
Adolfo Campoverde
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 9 Printed on 1/24/2023 at 10:37 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
12 ELECTRICRAFT, INC.5 8.0 40.0
Notes:Created By: Rick Howland
13 Parada Painting Inc.2 10.0 20.0 70-RESIDUALS
AREA
Notes:Created By: Monica Weiss
27 212.0
Manpower Log's Attachments:
12. ELECTRICRAFT, INC.
4-11-2022 Daily Report.xls
13. Parada Painting Inc.
0411 PARADA STA.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 Yes 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 9 Printed on 1/24/2023 at 10:37 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
3 AHERN RENTAL 8.0 Yes 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
5 United Rental 8.0 Yes 11:25AM 00-GENERAL
Notes:loader
Created By: Daniel Ford
6 United Rental Yes 10:15AM
Notes:Water truck
Created By: Daniel Ford
7 AHERN RENTAL 8.0 Yes 02:10PM
Notes:35' Ariel lift
Created By: Daniel Ford
8 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 10:05AM Airgas Welding Harness
Comments:Created By: Monica Weiss
2 10:05AM B & B Steel Supply w AIS Angle Brackets
Comments:Created By: Monica Weiss
3 10:05AM Burt Industrial 106046 Fire Hose
Comments:Created By: Monica Weiss
4 10:05AM Zima Corporation Stairs
Comments:Created By: Monica Weiss
5 10:05AM PRW Steel 471-270 Flat Bar
Comments:Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 5 of 9 Printed on 1/24/2023 at 10:37 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
6 10:05AM PRW Steel SQ Tube
Comments:Created By: Monica Weiss
7 10:05AM HD Supply White Cap 46661935 SAFETY
Comments:Created By: Monica Weiss
8 10:05AM HD Supply White Cap 46706690 Set 3 orientation
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.04.11 Airgas Welding Harness.pdf
2.
2022.04.11 B N B Steel Supply AIS MW.pdf
FBV Morro Bay Joint Venture Page 6 of 9 Printed on 1/24/2023 at 10:37 AM PST
3.
2022.04.11 Burt Industrial Supply Fire Hose 106046.pdf
4.
2022.04.11 Kusters Zima Stairs.pdf
5.
2022.04.11 Prw Steel 471-270 Flat Bar.pdf
FBV Morro Bay Joint Venture Page 7 of 9 Printed on 1/24/2023 at 10:37 AM PST
6.
2022.04.11 PRW Steel SQ Tube Galv.pdf
7.
2022.04.11 White Cap 46661935 Safety.pdf
8.
2022.04.11 White Cap 46706690 Set 3G.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
45°F 54°F 50°F 0.01 in.0.01 in.0.01 in.53%75%90%42°F 7.9 mph 16 mph 28 mph
FBV Morro Bay Joint Venture Page 8 of 9 Printed on 1/24/2023 at 10:37 AM PST
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
45°F
Clear
53°F
Partly Cloudy
53°F
Partly Cloudy
53°F
Clear
52°F
Clear
49°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 06:45:00 AM No