Daily Log: Friday 4/15/2022
Daily Log Completed
The Daily Log was completed by Monica Weiss on Wed May 4, 2022 at 10:32amPDT.
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Watering hydroseed
- landscaping sub grade continues to be worked on
- General clean up around site.We are gathering up all rebar
and removing all big rocks and concrete spoils in al landscape
areas
- Jobsite clean up
- Installing drain line and backfill outside of the chemical
building
_ working on BMP and getting ready for possible rain over the
weekemd
2 Daniel Ford No 50-RO/UV BUILDING - Fabrication and installation continue of PVC and CPVC pipes
- Fab and install the analyzer line
- Chemical injection quills are being installed
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- Pipe supports for the tanks and drilling for anchors
- SUEZ continues with there testing
- The chemical quills are being installed in the RO feed area
4 Daniel Ford No 90-CHEMICAL FACILITY - Fabricate and install the 1 1/2 inch cs lines in this area
- Piping continues to be installed in this area.
- Pipe supports are being worked on in this building
5 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
- Pipe supports are being worked on in this area
6 Daniel Ford No 20-HEADWORKS AREA>24-
Headworks Area - Vactor
Washdown
- We are digging around the 6 inch drain line in the bottom of
the vacor pad.
FBV Morro Bay Joint Venture Page 1 of 8 Printed on 1/24/2023 at 10:39 AM PST
NOTES LOG
No.Created By Issue?Location Comments
7 Daniel Ford No 20-HEADWORKS AREA>24-
Headworks Area - Vactor
Washdown
- We are building a weir wall in the vanhole directly after the
vacor pad
8 Daniel Ford No 96-MAINTENANCE
BUILDING
- Punch list
- Concrete items are being worked on today
MANPOWER LOG 22 Workers | 127.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.5 5.0 25.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Charlie Gonzales
Angel Diaz
Norman Gularte
Daniel Waddle
Manny Hernandez
Esteban Zamudio
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.2 6.0 12.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Javier Trevino
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.2 4.0 8.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Orlando Cortez
Andrew Seleva
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.3 5.0 15.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Micha Pixley
FBV Morro Bay Joint Venture Page 2 of 8 Printed on 1/24/2023 at 10:39 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Enrique Padilla
Rafael Alvarado
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.2 6.0 12.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 5.0 5.0
Notes:Cement Mason
Daniel Sheslingoff
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 5.0 5.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Cement Masons
Adolfo Campoverde
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 5.0 5.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
10 ELECTRICRAFT, INC.4 8.0 32.0
Notes:Created By: Rick Howland
22 127.0
Manpower Log's Attachments:
10. ELECTRICRAFT, INC.
4-15-2022 Daily Report.xls
FBV Morro Bay Joint Venture Page 3 of 8 Printed on 1/24/2023 at 10:39 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 Yes 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 Yes 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
5 United Rental 8.0 Yes 11:25AM 00-GENERAL
Notes:loader
Created By: Daniel Ford
6 United Rental Yes 10:15AM
Notes:Water truck
Created By: Daniel Ford
7 AHERN RENTAL 8.0 Yes 02:10PM
Notes:35' Ariel lift
Created By: Daniel Ford
8 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 10:25AM Airgas 3238 Misc. Weld
Comments:Created By: Monica Weiss
2 10:25AM Airgas 6783 Helium
Comments:Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 4 of 8 Printed on 1/24/2023 at 10:39 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
3 10:25AM Ferguson Enterprises, LLC drain Grates
Comments:Created By: Monica Weiss
4 10:25AM HARRINGTON INDUSTRIAL
PLASTICS LLC
solenoid valve
Comments:Created By: Monica Weiss
5 10:25AM Miner's Ace Hardware Tools
Comments:Created By: Monica Weiss
6 10:25AM Miner's Ace Hardware 735390 Replacement Tools
Comments:Created By: Monica Weiss
7 10:25AM Suez Water Technologies &
Solutions
ANtenna
Comments:Created By: Monica Weiss
8 10:25AM HD Supply White Cap 46661935 Water SAFETY
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.04.15 Airgas 3238 Misc Weld.pdf
FBV Morro Bay Joint Venture Page 5 of 8 Printed on 1/24/2023 at 10:39 AM PST
2.
2022.04.15 Airgas 6783 Helium.pdf
3.
2022.04.15 Ferguson Drain Grates.pdf
4.
2022.04.15 Harrington ASCO Solenoid Vlv.pdf
FBV Morro Bay Joint Venture Page 6 of 8 Printed on 1/24/2023 at 10:39 AM PST
5.
2022.04.15 Miner Tools.pdf
6.
2022.04.15 Miners 735390 Replacement To0ls.pdf
7.
2022.04.15 Suez antenna.pdf
FBV Morro Bay Joint Venture Page 7 of 8 Printed on 1/24/2023 at 10:39 AM PST
8.
2022.04.15 White Cap 46661935 Water.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
44°F 59°F 51°F 0.00 in.0.00 in.0.00 in.71%86%98%47°F 4.8 mph 10 mph 13 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
45°F
Clear
53°F
Partly Cloudy
59°F
Cloudy
58°F
Cloudy
54°F
Cloudy
50°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:50:00 AM No
By Date Copies To