HomeMy WebLinkAbout2022-04-21FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Thursday 4/21/2022
Daily Log Completed
The Daily Log was completed by Monica Weiss on Wed May 4, 2022 at 03:52pmPDT.
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - landscaping sub grade continues to be worked on
- Installing drain line and backfill outside of the chemical
building
- We are stripping out the formwork the weir wall in manhole
1
- Cleaning out manholes and working with the cement mason
in the chemical
- We were moving water around for testing and supporting
the pump testing
- Enrique was helping in the office
- Rain event
2 Daniel Ford No 50-RO/UV BUILDING - Fabrication and installation continue of PVC and CPVC pipes
- Fab and install the analyzer line
- Chemical injection quills are being installed
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- Pipe supports for the tanks and drilling for anchors
- SUEZ continues with there testing
- The chemical quills are being installed in the RO feed area
- Commissioning pumps and valves at the MBR slab
4 Daniel Ford No 90-CHEMICAL FACILITY - Fabricate and install the 1 1/2 inch cs lines in this area
- Piping continues to be installed in this area.
- Pipe supports are being worked on in this building
- We are working on the 2" containment
- We are working on the supports
- Big Wachoo Had 2 guys working on the fencing around this
building today
5 Daniel Ford No 20-HEADWORKS AREA>24-
Headworks Area - Vactor
Washdown
- Some patch work and cleaning in MH 1
FBV Morro Bay Joint Venture Page 1 of 6 Printed on 1/24/2023 at 10:41 AM PST
NOTES LOG
No.Created By Issue?Location Comments
6 Daniel Ford No 96-MAINTENANCE
BUILDING
- Punch list
- Concrete items are being worked on today
MANPOWER LOG 20 Workers | 159.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Charlie Gonzales
Angel Diaz
Daniel Waddle
Manny Hernandez
Esteban Zamudio
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:LABORER APPRENTICE
Javier Trevino
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 7.0 7.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Andrew Seleva
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Rafael Alvarado
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.2 6.0 12.0 00-GENERAL
Notes:Operator
Trevor Hernandez
FBV Morro Bay Joint Venture Page 2 of 6 Printed on 1/24/2023 at 10:41 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Kyle Brooking
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Cement Masons
Adolfo Campoverde
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
10 ELECTRICRAFT, INC.4 8.0 32.0
Notes:Created By: Rick Howland
11 Parada Painting Inc.2 10.0 20.0
Notes:Created By: Monica Weiss
20 159.0
Manpower Log's Attachments:
10. ELECTRICRAFT, INC.
4-21-2022 Daily Report.xls
FBV Morro Bay Joint Venture Page 3 of 6 Printed on 1/24/2023 at 10:41 AM PST
11. Parada Painting Inc.
0421 PARADA STA.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 Yes 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 Yes 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
5 United Rental 8.0 Yes 11:25AM 00-GENERAL
Notes:loader
Created By: Daniel Ford
6 United Rental Yes 10:15AM
Notes:Water truck
Created By: Daniel Ford
7 AHERN RENTAL 8.0 Yes 02:10PM
Notes:35' Ariel lift
Created By: Daniel Ford
8 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
FBV Morro Bay Joint Venture Page 4 of 6 Printed on 1/24/2023 at 10:41 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 03:40PM HARRINGTON INDUSTRIAL
PLASTICS LLC
471-277 CPVC CAP SWEEP
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.04.21 Harrington 471-277 CPVC Cap Sweep.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
52°F 60°F 55°F 0.25 in.0.25 in.0.26 in.76%86%93%51°F 6.7 mph 11 mph 16 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Partly Cloudy
54°F
Rain
54°F
Cloudy
60°F
Cloudy
58°F
Rain
54°F
Rain
54°F
FBV Morro Bay Joint Venture Page 5 of 6 Printed on 1/24/2023 at 10:41 AM PST
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 07:00:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 6 of 6 Printed on 1/24/2023 at 10:41 AM PST