Daily Log: Wednesday 4/27/2022
Daily Log Completed
The Daily Log was completed by Monica Weiss on Thu May 5, 2022 at 11:22amPDT.
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Excavating across the road in the front for the gas line. (We
have traffic control setup as well as steel plates)
- We were moving water around for testing and supporting
the pump testing
- Jobsite clean up
- Watering hydroseed
- landscaping sub grade continues
- The Cement Masons are working on all vaults and concrete
that touch the asphalt
2 Daniel Ford No 50-RO/UV BUILDING - We are working on the 8 inch valves
- Fab and install the analyzer line
- Chemical injection quills are being installed
- The neutralizer tanks are being worked on, mixers being
installed etc.
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- Pipe supports for the tanks and drilling for anchors
- SUEZ continues with there testing
4 Daniel Ford No 90-CHEMICAL FACILITY - Fabricate and install the 1 1/2 inch cs lines in this area
- Piping continues to be installed in this area.
- We are working on the supports
- Eye wash stations are being installed
- We are installing the copper lines
5 Daniel Ford No 96-MAINTENANCE
BUILDING
- Punch list
- Concrete items are being worked on today
6 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
-Water is being pumped out of the north and south tanks
FBV Morro Bay Joint Venture Page 1 of 9 Printed on 1/24/2023 at 10:43 AM PST
NOTES LOG
No.Created By Issue?Location Comments
7 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
- We were working on the anchors for the Conveyor today
- Pickling of all welds for the conveyor is happening today
8 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- The grating for over the mixing chimney arrived today. we
had to do some modifications for it to fit correctly.
9 Daniel Ford No 60-PRODUCT WATER
AREA>61-Product Water
Area - Calcite Contactor
- We moved the 2 in ch chemical lines to line up with the
injection ports in this area
MANPOWER LOG 19 Workers | 148.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Charlie Gonzales
Angel Diaz
Daniel Waddle
Manny Hernandez
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:LABORER APPRENTICE
Javier Trevino
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CARPENTER APPRENTICE
FBV Morro Bay Joint Venture Page 2 of 9 Printed on 1/24/2023 at 10:43 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Rafael Alvarado
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.2 6.0 12.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Cement Masons
Adolfo Campoverde
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
11 ELECTRICRAFT, INC.5 8.0 40.0
Notes:Created By: Rick Howland
19 148.0
Manpower Log's Attachments:
11. ELECTRICRAFT, INC.
FBV Morro Bay Joint Venture Page 3 of 9 Printed on 1/24/2023 at 10:43 AM PST
4-27-2022 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 Yes 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 Yes 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
5 United Rental 8.0 Yes 11:25AM 00-GENERAL
Notes:loader
Created By: Daniel Ford
6 United Rental Yes 10:15AM
Notes:Water truck
Created By: Daniel Ford
7 AHERN RENTAL 8.0 Yes 02:10PM
Notes:35' Ariel lift
Created By: Daniel Ford
8 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 10:20AM Burt Industrial 471-280
Comments:Created By: Monica Weiss
2 10:20AM Ferguson Enterprises, LLC 1" CPVC
Comments:Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 4 of 9 Printed on 1/24/2023 at 10:43 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
3 10:20AM Ferguson Enterprises, LLC Wax Tape
Comments:Created By: Monica Weiss
4 10:20AM HARRINGTON INDUSTRIAL
PLASTICS LLC
471-277 A90
Comments:Created By: Monica Weiss
5 10:20AM HARRINGTON INDUSTRIAL
PLASTICS LLC
477-286 A90
Comments:Created By: Monica Weiss
6 10:20AM HARRINGTON INDUSTRIAL
PLASTICS LLC
MR145
Comments:Created By: Monica Weiss
7 10:20AM McMaster-CARR A90 Bulkhead
Comments:Created By: Monica Weiss
8 10:20AM Suez Water Technologies &
Solutions
Burkert Pnue Valve
Comments:Created By: Monica Weiss
9 10:20AM HD Supply White Cap 46939596 Safety
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.04.27 Burt Ind 471-280.pdf
FBV Morro Bay Joint Venture Page 5 of 9 Printed on 1/24/2023 at 10:43 AM PST
2.
2022.04.27 Ferguson 1in CPVC.pdf
3.
2022.04.27 Ferguson Trenton Wax Tape.pdf
4.
2022.04.27 Harrington 471-277 A90.pdf
FBV Morro Bay Joint Venture Page 6 of 9 Printed on 1/24/2023 at 10:43 AM PST
5.
2022.04.27 Harrington 471-286 A90.pdf
6.
2022.04.27 Harrington MR145.pdf
7.
2022.04.27 McMaster Carr Bulkhead A90.pdf
FBV Morro Bay Joint Venture Page 7 of 9 Printed on 1/24/2023 at 10:43 AM PST
8.
2022.04.27 Suez Burkert Pnu Valve.pdf
9.
2022.04.27 White Cap 46939596 SAFETY.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
44°F 55°F 50°F 0.00 in.0.00 in.0.00 in.70%83%95%45°F 6.8 mph 11 mph 21 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
46°F
Clear
52°F
Partly Cloudy
55°F
Partly Cloudy
56°F
Clear
54°F
Partly Cloudy
50°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:50:00 AM No
FBV Morro Bay Joint Venture Page 8 of 9 Printed on 1/24/2023 at 10:43 AM PST
By Date Copies To