HomeMy WebLinkAbout2022-04-29FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Friday 4/29/2022
Daily Log Completed
The Daily Log was completed by Monica Weiss on Thu May 5, 2022 at 02:22pmPDT.
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - We placed 15 yards of slurry across the road in the front for
the gas line. (We have traffic control setup as well as steel
plates)
- Jobsite clean up
- landscaping sub grade continues
- The Cement Masons are Placing concrete in the vacor pad
and a small pad on the SE corner of the MBNR slab
- We discovered a leak in one of the lines. We are going to dig
it up and make the repair
- We are working on the ravine area
2 Daniel Ford No 50-RO/UV BUILDING - This whole building has been cleaned and organized
- Welding the chem line for this building
- The neutralizer tanks are being worked on, mixers being
installed etc.
- The chem piping is being welded in this area
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- SUEZ continues with there testing
- pickling of welds is happening in this area
4 Daniel Ford No 90-CHEMICAL FACILITY - Piping continues to be installed in this area.
- We are working on the supports
- We are installing the copper lines
5 Daniel Ford No 96-MAINTENANCE
BUILDING
- Punch list
- Concrete items are being worked on today
6 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
- Water is being pumped out of the north and south tanks
- We cleaned out the middle tank
FBV Morro Bay Joint Venture Page 1 of 9 Printed on 1/24/2023 at 10:44 AM PST
NOTES LOG
No.Created By Issue?Location Comments
7 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
- We were working on the anchors for the Conveyor today
- Pickling of all welds for the conveyor is happening today
8 Daniel Ford No 60-PRODUCT WATER
AREA>61-Product Water
Area - Calcite Contactor
- We cleaned the pumps in this area
- We moved 3 chemical injection lines and backfiled them
- The drain on the northside had to be lowered before asphalt
is laid down we dug it up and lowered it a few inches.
MANPOWER LOG 19 Workers | 148.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Charlie Gonzales
Angel Diaz
Daniel Waddle
Manny Hernandez
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:LABORER APPRENTICE
Javier Trevino
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Rafael Alvarado
FBV Morro Bay Joint Venture Page 2 of 9 Printed on 1/24/2023 at 10:44 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.2 6.0 12.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Cement Masons
Adolfo Campoverde
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
11 ELECTRICRAFT, INC.5 8.0 40.0
Notes:Created By: Rick Howland
19 148.0
Manpower Log's Attachments:
11. ELECTRICRAFT, INC.
4-29-2022 Daily Report.xls
FBV Morro Bay Joint Venture Page 3 of 9 Printed on 1/24/2023 at 10:44 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 Yes 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 Yes 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
5 United Rental 8.0 Yes 11:25AM 00-GENERAL
Notes:loader
Created By: Daniel Ford
6 United Rental Yes 10:15AM
Notes:Water truck
Created By: Daniel Ford
7 AHERN RENTAL 8.0 Yes 02:10PM
Notes:35' Ariel lift
Created By: Daniel Ford
8 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 11:25AM Airgas 1596 Safety Filters
Comments:Created By: Monica Weiss
2 11:25AM Airgas 2575 Argon Blades
Comments:Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 4 of 9 Printed on 1/24/2023 at 10:44 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
3 11:25AM Airgas 2495 Pipe Wrap
Comments:Created By: Monica Weiss
4 11:25AM CalPortland BLD 20 Concrete
Comments:Created By: Monica Weiss
5 11:25AM CalPortland Sand Slurry
Comments:GAS
Created By: Monica Weiss
6 11:25AM Amerisafe Group Fall Protection Video
Comments:Created By: Monica Weiss
7 11:25AM Grainger Copper Fittings
Comments:Created By: Monica Weiss
8 11:25AM HARRINGTON INDUSTRIAL
PLASTICS LLC
2in 90 LS (3)
Comments:Created By: Monica Weiss
9 11:25AM HARRINGTON INDUSTRIAL
PLASTICS LLC
MR145
Comments:Created By: Monica Weiss
10 11:25AM HD Supply White Cap 47002282 Bolts
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.04.29 Airgas 1596 Filter.pdf
FBV Morro Bay Joint Venture Page 5 of 9 Printed on 1/24/2023 at 10:44 AM PST
2.
2022.04.29 Airgas 2575 argon blades.pdf
3.
2022.04.29 Airgas Pipe wrap 2495.pdf
4.
2022.04.29 Calportland BLD 20 Concrete.pdf
FBV Morro Bay Joint Venture Page 6 of 9 Printed on 1/24/2023 at 10:44 AM PST
5.
2022.04.29 Calportland Sand Slurry Gas.pdf
6.
2022.04.29 Fall Protection Video.pdf
7.
2022.04.29 Grainger Copper.pdf
FBV Morro Bay Joint Venture Page 7 of 9 Printed on 1/24/2023 at 10:44 AM PST
8.
2022.04.29 Harrington 2in 90 LS x3.pdf
9.
2022.04.29 Harrington MR145.pdf
10.
2022.04.29 White Cap 47002282 Bolt.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
46°F 64°F 53°F 0.00 in.0.00 in.0.00 in.54%73%90%45°F 4.0 mph 9 mph 14 mph
FBV Morro Bay Joint Venture Page 8 of 9 Printed on 1/24/2023 at 10:44 AM PST
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
51°F
Clear
56°F
Clear
55°F
Clear
54°F
Clear
60°F
Clear
53°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:50:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 9 of 9 Printed on 1/24/2023 at 10:44 AM PST