HomeMy WebLinkAbout2022-05-02FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Monday 5/2/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL
- Jobsite clean up
- landscaping sub grade continues
- The Cement Masons Are fixing up all surfaces in preparation
for asphalt
- We discovered a leak in one of the lines. We are going to dig
it up and make the repair for the Prw
2 Daniel Ford No 50-RO/UV BUILDING - fad and install SS supports for the UV reactor
- bolt up al over in the RO
- The neutralizer tanks are being worked on, mixers being
installed etc.
- The chem piping is being welded in this area
3 Daniel Ford No 90-CHEMICAL FACILITY - We are installing supports
- We are working on the supports
- We are installing the copper lines
4 Daniel Ford No 60-PRODUCT WATER
AREA>61-Product Water
Area - Calcite Contactor
- We stubbed up 3 chemical injection sites for the calcite
contractor today
MANPOWER LOG 16 Workers | 114.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Angel Diaz
Manny Hernandez
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 1 of 10 Printed on 1/24/2023 at 10:45 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Rafael Alvarado
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 6.0 6.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
9 Dahl Insulation 1 8.0 8.0 00-GENERAL
Notes:Fall protection training, site specific orientation, material staging, job walk
Created By: Eric Girten
FBV Morro Bay Joint Venture Page 2 of 10 Printed on 1/24/2023 at 10:45 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
10 Dahl Insulation 2 2.0 4.0 00-GENERAL
Notes:Created By: Eric Girten
11 ELECTRICRAFT, INC.4 8.0 32.0
Notes:Created By: Rick Howland
16 114.0
Manpower Log's Attachments:
10. Dahl Insulation
0502 DAHL JHA.pdf
11. ELECTRICRAFT, INC.
5-2-2022 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 Yes 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 Yes 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 10 Printed on 1/24/2023 at 10:45 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
4 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
5 United Rental 8.0 Yes 11:25AM 00-GENERAL
Notes:loader
Created By: Daniel Ford
6 United Rental Yes 10:15AM
Notes:Water truck
Created By: Daniel Ford
7 AHERN RENTAL 8.0 Yes 02:10PM
Notes:35' Ariel lift
Created By: Daniel Ford
8 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 12:05PM Burt Industrial FREQ HOSE
Comments:Created By: Monica Weiss
2 12:05PM Ferguson Enterprises, LLC 471-289 Yard Pipe
Comments:Created By: Monica Weiss
3 12:05PM Ferguson Enterprises, LLC CREDIT Copper Fittings
Comments:Created By: Monica Weiss
4 12:05PM Ferguson Enterprises, LLC Eye Wash Fittings
Comments:Created By: Monica Weiss
5 12:05PM HARRINGTON INDUSTRIAL
PLASTICS LLC
471-296 CPVC Fittings
Comments:A90
Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 4 of 10 Printed on 1/24/2023 at 10:45 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
6 12:05PM HARRINGTON INDUSTRIAL
PLASTICS LLC
MR Gaskets
Comments:Created By: Monica Weiss
7 12:05PM MID-STATE CONCRETE
PRODUCTS, LLC
K-Rail
Comments:Created By: Monica Weiss
8 12:05PM Miner's Ace Hardware 736778 Consumables
Comments:Created By: Monica Weiss
9 12:05PM Miner's Ace Hardware 736780 Fasteners
Comments:Created By: Monica Weiss
10 12:05PM NEGRANTI & SONS 33633
Comments:Created By: Monica Weiss
11 12:05PM Suez Water Technologies &
Solutions
Compressor Pressure Switch
Comments:Created By: Monica Weiss
12 12:05PM HD Supply White Cap 46992094 Grinder
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.05.02 Burt Ind YP Hose.pdf
FBV Morro Bay Joint Venture Page 5 of 10 Printed on 1/24/2023 at 10:45 AM PST
2.
2022.05.02 Ferguson 471-289 YP.pdf
3.
2022.05.02 Ferguson Credit Copper.pdf
4.
2022.05.02 Ferguson Eye Wash.pdf
FBV Morro Bay Joint Venture Page 6 of 10 Printed on 1/24/2023 at 10:45 AM PST
5.
2022.05.02 Harrington 471-296 A90 .pdf
6.
2022.05.02 Harrington MR Gaskets.pdf
7.
2022.05.02 Mid-State Concrete K-rail.pdf
FBV Morro Bay Joint Venture Page 7 of 10 Printed on 1/24/2023 at 10:45 AM PST
8.
2022.05.02 Miners 736778 Cons.pdf
9.
2022.05.02 Miners 736780 Fasteners.pdf
10.
2022.05.02 Negranti 33633 .pdf
FBV Morro Bay Joint Venture Page 8 of 10 Printed on 1/24/2023 at 10:45 AM PST
11.
2022.05.02 Suez Compressor Pressure Switch.pdf
12.
2022.05.02 White Cap 46992094 Grinder.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
46°F 56°F 51°F 0.00 in.0.00 in.0.00 in.74%86%96%47°F 6.7 mph 13 mph 23 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
48°F
Clear
49°F
Clear
56°F
Clear
55°F
Clear
54°F
Clear
50°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 06:35:00 AM No