HomeMy WebLinkAbout2022-05-03FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Tuesday 5/3/2022
Daily Log Completed
The Daily Log was completed by Monica Weiss on Wed Jun 1, 2022 at 03:13pmPDT.
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL
- Jobsite clean up
- landscaping sub grade continues
- The Cement Masons Are fixing up all surfaces in preparation
for asphalt
-Pressure testing for the PRW line is on going
2 Daniel Ford No 50-RO/UV BUILDING - fad and install SS supports for the UV reactor
- bolt up al over in the RO
- The neutralizer tanks are being worked on, mixers being
installed etc.
- The chem piping is being welded in this area
3 Daniel Ford No 90-CHEMICAL FACILITY - We are installing supports
- We are working on the supports
- We are installing the copper lines
4 Daniel Ford No 60-PRODUCT WATER
AREA>61-Product Water
Area - Calcite Contactor
- We stubbed up 3 chemical injection sites for the calcite
contractor today
5 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- we did maintenance in this area. -All pumps were cycled and
we ran the water here for over 20 minutes.
6 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- we did maintenance in this area. -All pumps were cycled and
we ran the water here for over 20 minutes.
FBV Morro Bay Joint Venture Page 1 of 10 Printed on 1/24/2023 at 10:45 AM PST
MANPOWER LOG 16 Workers | 130.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Angel Diaz
Manny Hernandez
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.0 8.0 0.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Orlando Cortez
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Enrique Padilla
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 6.0 6.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 10 Printed on 1/24/2023 at 10:45 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
9 Dahl Insulation 1 8.0 8.0 30-TREATMENT
AREA
Notes:Created By: Eric Girten
10 ELECTRICRAFT, INC.4 8.0 32.0
Notes:Created By: Rick Howland
11 Parada Painting Inc.2 10.0 20.0
Notes:Created By: Monica Weiss
12 1 8.0 8.0
Notes:Created By: Monica Weiss
16 130.0
Manpower Log's Attachments:
10. ELECTRICRAFT, INC.
5-3-2022 Daily Report.xls
11. Parada Painting Inc.
0503 PARADA STA.pdf
FBV Morro Bay Joint Venture Page 3 of 10 Printed on 1/24/2023 at 10:45 AM PST
12.
0503 DAHL STA.pdf 0503 DAHL STA.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 Yes 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 Yes 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
5 AHERN RENTAL 8.0 Yes 02:10PM
Notes:35' Ariel lift
Created By: Daniel Ford
6 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 10 Printed on 1/24/2023 at 10:45 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 12:35PM CAPITAL FLOW INC 471-294
Comments:Created By: Monica Weiss
2 12:35PM CAPITAL FLOW INC Carbon Steel Valves
Comments:Created By: Monica Weiss
3 12:35PM CAPITAL FLOW INC TR004 Carbon steel fittings
Comments:Created By: Monica Weiss
4 12:35PM Fastenal 0824 Bolts and Wedge anchors
Comments:Created By: Monica Weiss
5 12:35PM Ferguson Enterprises, LLC 471-289 Yard Fittings
Comments:Created By: Monica Weiss
6 12:35PM Ferguson Enterprises, LLC 471-290 Yard Piping
Comments:Stainless Steel Ball Valves
Created By: Monica Weiss
7 12:35PM Ferguson Enterprises, LLC A73 FREQ
Comments:Created By: Monica Weiss
8 12:55PM Ferguson Enterprises, LLC Water Heater
Comments:Created By: Monica Weiss
9 12:55PM HARRINGTON INDUSTRIAL
PLASTICS LLC
FRP DBL Strut
Comments:Created By: Monica Weiss
10 12:55PM HARRINGTON INDUSTRIAL
PLASTICS LLC
MR90 3in Diaphragm Valve
Comments:Created By: Monica Weiss
11 12:55PM Miner's Ace Hardware 736860 A30
Comments:Created By: Monica Weiss
12 12:55PM Parada Painting Inc.Tnemec Paint
Comments:Created By: Monica Weiss
13 12:55PM USA Blue Book Dechlor Tablets Sample DPD
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
FBV Morro Bay Joint Venture Page 5 of 10 Printed on 1/24/2023 at 10:45 AM PST
1.
2022.05.03 Capflo 471-294.pdf
2.
2022.05.03 Capflo CS Valves .pdf
3.
2022.05.03 Capflo CS Valves .pdf
FBV Morro Bay Joint Venture Page 6 of 10 Printed on 1/24/2023 at 10:45 AM PST
4.
2022.05.03 Fastenal 0824.pdf
5.
2022.05.03 Ferguson 471-289 YP.pdf
6.
2022.05.03 Ferguson 471-290 .pdf
FBV Morro Bay Joint Venture Page 7 of 10 Printed on 1/24/2023 at 10:45 AM PST
7.
2022.05.03 Ferguson A73 FREQ.pdf
8.
2022.05.03 Ferguson WH Chronomite Elmco.pdf
9.
2022.05.03 Harrington FRP Dbl Strut.pdf
FBV Morro Bay Joint Venture Page 8 of 10 Printed on 1/24/2023 at 10:45 AM PST
10.
2022.05.03 Harrington MR A90 3in Dia Vlv .pdf
11.
2022.05.03 Miners 736860 A30.pdf
12.
2022.05.03 Parada Paint.pdf
FBV Morro Bay Joint Venture Page 9 of 10 Printed on 1/24/2023 at 10:45 AM PST
13.
2022.05.03 USA Bluebook Chlorine.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
45°F 60°F 53°F 0.00 in.0.00 in.0.00 in.44%73%89%44°F 5.1 mph 8 mph 14 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
50°F
Clear
61°F
Clear
57°F
Clear
57°F
Clear
56°F
Clear
52°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:45:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 10 of 10 Printed on 1/24/2023 at 10:45 AM PST