HomeMy WebLinkAbout2022-05-04FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Wednesday 5/4/2022
Daily Log Completed
The Daily Log was completed by Monica Weiss on Thu Jun 2, 2022 at 07:04amPDT.
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL
- Jobsite clean up
- landscaping sub grade continues
- The Cement Mason is fixing up all surfaces in preparation for
asphalt
- Pressure testing and repairing leaks for the PRW line is on
going
2 Daniel Ford No 50-RO/UV BUILDING - Anchorage for UV supports
- Drain lines
- The neutralizer tanks are being worked on, mixers being
installed etc.
- The chem piping is being welded in this area
- RO bolt up is ongoing
3 Daniel Ford No 90-CHEMICAL FACILITY - Supports Are being installed
- Fad, install, and weld the chemical piping
- We are installing the copper lines
4 Daniel Ford No 60-PRODUCT WATER
AREA>63-Product Water -
IPR Product Water Pump
Station
- The sample line was worked on in this area
5 Daniel Ford No 70-RESIDUALS AREA>73-
Residuals Area - SAFE Filter
System
- Weekly maintenance was done for area 73 and 72
- We are working on pipe supports in this area
- The coupler for the SAFE for the ARV has been welded
6 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
-Supports for the Cassette tank were welded today
FBV Morro Bay Joint Venture Page 1 of 6 Printed on 1/24/2023 at 10:52 AM PST
MANPOWER LOG 15 Workers | 112.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 Dahl Insulation 2 8.0 16.0 30-TREATMENT
AREA
Notes:Created By: Eric Girten
2 Dahl Insulation 1 2.0 2.0 00-GENERAL
Notes:Created By: Eric Girten
3 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Angel Diaz
Manny Hernandez
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.0 8.0 0.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Orlando Cortez
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Enrique Padilla
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 6.0 6.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 6 Printed on 1/24/2023 at 10:52 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
11 ELECTRICRAFT, INC.4 8.0 32.0
Notes:Created By: Rick Howland
15 112.0
Manpower Log's Attachments:
2. Dahl Insulation
0504 DAHL STA.pdf
11. ELECTRICRAFT, INC.
5-4-2022 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 Yes 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 05:40AM
Notes:45' ariel lift
FBV Morro Bay Joint Venture Page 3 of 6 Printed on 1/24/2023 at 10:52 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
Created By: Daniel Ford
3 AHERN RENTAL 8.0 Yes 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
5 AHERN RENTAL 8.0 Yes 02:10PM
Notes:35' Ariel lift
Created By: Daniel Ford
6 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 06:55AM Ferguson Enterprises, LLC A90 Eye wash Plumbing
Comments:Created By: Monica Weiss
2 06:55AM Ferguson Enterprises, LLC
Comments:AIS
Created By: Monica Weiss
3 06:55AM Miner's Ace Hardware 737020 YP
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
FBV Morro Bay Joint Venture Page 4 of 6 Printed on 1/24/2023 at 10:52 AM PST
1.
2022.05.04 Ferguson Eyewash A90.pdf
2.
2022.05.04 Ferguson AIS Ball Valve mill.pdf
3.
2022.05.04 Miners 737020 YP .pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
46°F 57°F 52°F 0.00 in.0.00 in.0.00 in.51%82%94%46°F 4.0 mph 7 mph 10 mph
FBV Morro Bay Joint Venture Page 5 of 6 Printed on 1/24/2023 at 10:52 AM PST
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
51°F
Clear
56°F
Clear
57°F
Clear
53°F
Clear
51°F
Clear
49°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:45:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 6 of 6 Printed on 1/24/2023 at 10:52 AM PST