HomeMy WebLinkAbout2022-05-07FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Saturday 5/7/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL
- Jobsite clean up
- landscaping sub grade continues
- The Cement Mason is fixing up all surfaces in preparation for
asphalt
- Pressure testing and repairing leaks for the PRW line
2 Daniel Ford No 90-CHEMICAL FACILITY - Supports Are being installed
- Fad, install, and weld the chemical piping
- Pressure switches for the Air tank are being installed
- The auto drain for the air tank relief valve is being installed
-
3 Daniel Ford No 70-RESIDUALS AREA>73-
Residuals Area - SAFE Filter
System
- Support and install for the extra hose bib in this area.
-
4 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- Holles for supports are being drilled
- Remove and Replace the 12" Butterfly valve on the east RO
feed tank (shave PVC)
- All thread for the cassette tank is being cut
MANPOWER LOG 9 Workers | 72.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 ELECTRICRAFT, INC.6 8.0 48.0
Notes:Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Orlando Cortez
FBV Morro Bay Joint Venture Page 1 of 3 Printed on 1/24/2023 at 10:54 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Rick Jenne
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Enrique Padilla
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
9 72.0
Manpower Log's Attachments:
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 Yes 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 Yes 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
5 AHERN RENTAL 8.0 Yes 02:10PM
Notes:35' Ariel lift
Created By: Daniel Ford
6 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 3 Printed on 1/24/2023 at 10:54 AM PST
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
50°F 57°F 53°F 0.00 in.0.00 in.0.00 in.73%85%99%49°F 7.5 mph 16 mph 25 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Partly Cloudy
50°F
Clear
53°F
Clear
57°F
Clear
57°F
Clear
56°F
Clear
53°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 06:15:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 3 of 3 Printed on 1/24/2023 at 10:54 AM PST