Daily Log: Thursday 5/12/2022
Daily Log Completed
The Daily Log was completed by Monica Weiss on Thu Jun 2, 2022 at 09:31amPDT.
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - The Cement Mason is bushing down the concrete in the
outside storage buildings where the concrete is to high for the
asphalt.
- Repairs are being made to the PRW and PW line.
- Mowing the weeds down
2 Daniel Ford No 50-RO/UV BUILDING - Anchorage for UV supports
- Drain lines
- RO bolt up is ongoing
3 Daniel Ford No 90-CHEMICAL FACILITY - Copper supports are being installed
- Fad, install, and weld the chemical piping
- welds are being passivated
- Welding for the C20 and install area happening
4 Daniel Ford No 10-SITE OVERALL - We performed maintenance by running water through the
entire safe filter system and cycling water over the entire
jobsite
5 Daniel Ford No 60-PRODUCT WATER AREA - Maintenance was performed on all outfall and IPR pumps
MANPOWER LOG 12 Workers | 100.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Angel Diaz
Manny Hernandez
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 10:55 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
2 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Orlando Cortez
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Enrique Padilla
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.0 8.0 0.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
9 Dahl Insulation 1 8.0 8.0 30-TREATMENT
AREA
Notes:Metal jacket insulated compressed air lines
Created By: Eric Girten
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 10:55 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
10 Parada Painting Inc.2 10.0 20.0
Notes:Created By: Monica Weiss
12 100.0
Manpower Log's Attachments:
9. Dahl Insulation
0512 DAHL STA.pdf
10. Parada Painting Inc.
0512 PARADA STA.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 Yes 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 05:40AM
Notes:45' ariel lift
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 10:55 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
Created By: Daniel Ford
3 AHERN RENTAL 8.0 Yes 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
5 AHERN RENTAL 8.0 Yes 02:10PM
Notes:35' Ariel lift
Created By: Daniel Ford
6 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 09:00AM Ferguson Enterprises, LLC 471-301
Comments:Created By: Monica Weiss
2 09:00AM Ferguson Enterprises, LLC Repair Coupling
Comments:Created By: Monica Weiss
3 09:00AM Miner's Ace Hardware 737676 Glue
Comments:Created By: Monica Weiss
4 09:00AM NEGRANTI & SONS 33608 Rip Rap
Comments:Created By: Monica Weiss
5 09:00AM TRI STAR INDUSTRIAL LLC 2693.015 Pipe Supports
Comments:Created By: Monica Weiss
6 09:00AM Trojan Technologies Start-up Binder
Comments:Created By: Monica Weiss
7 09:00AM HD Supply White Cap 47191700 Safety Items
Comments:Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 10:55 AM PST
Delivery Log's Attachments:
1.
2022.05.12 Ferguson 471-301.pdf
2.
2022.05.12 Ferguson Repair Coupling.pdf
3.
2022.05.12 Miners 737676 glue .pdf
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 10:55 AM PST
4.
2022.05.12 Negranti 33608.pdf
5.
2022.05.12 Tri-Star 2693.015.pdf
6.
2022.05.12 Trojan Start-up Binder.pdf
FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 10:55 AM PST
7.
2022.05.12 White Cap 47191700 Safety.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
46°F 60°F 52°F 0.00 in.0.00 in.0.00 in.48%71%91%43°F 4.7 mph 9 mph 14 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
49°F
Partly Cloudy
56°F
Cloudy
54°F
Clear
55°F
Clear
59°F
Clear
52°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 07:45:00 AM No
By Date Copies To