HomeMy WebLinkAbout2022-05-18FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Wednesday 5/18/2022
Daily Log Completed
The Daily Log was completed by Monica Weiss on Thu Jun 2, 2022 at 02:36pmPDT.
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Jobsite clean up
- Valve cans are being installed in various places around the
job and prep for asphalt is ongoing.
- Pond 2 is being backfilled
- All roads are being prepped for Granite
- Grading and reworking the fence at the front entrance.
- As builts for all manholes, pads, valve boxes and anything
else in the asphalt
- Loadout for the pile and hauling material to ravine
- Backfilling PRW leaks
- Hills are having the mustard plants mowed down.
2 Daniel Ford No 50-RO/UV BUILDING - The Reps for the RO and UV systems are on site.
- We routed the ROC into the sanitary lift station for the RO
rep.
3 Daniel Ford No 90-CHEMICAL FACILITY - Copper pipe is being run and supported
4 Daniel Ford No 10-SITE OVERALL - Scheduled maintenance is ongoing
5 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- The level sensors for the Cassette tank are being installed
- Pipe supports for the MBR slab are being welded
MANPOWER LOG 17 Workers | 140.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 Dahl Insulation 1 8.0 8.0 70-RESIDUALS
AREA
Notes:Insulate/metal jacket blower piping at residuals area
FBV Morro Bay Joint Venture Page 1 of 6 Printed on 1/24/2023 at 10:58 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Eric Girten
2 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Angel Diaz
Manny Hernandez
Jaren Unfried
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Orlando Cortez
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.0 8.0 0.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 6 Printed on 1/24/2023 at 10:58 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Laborers
Johnathan Torres
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Carpenters
Enrique Padilla
Created By: Daniel Ford
11 ELECTRICRAFT, INC.4 8.0 32.0
Notes:Created By: Rick Howland
12 Parada Painting Inc.2 10.0 20.0
Notes:Created By: Monica Weiss
17 140.0
Manpower Log's Attachments:
1. Dahl Insulation
0518 DAHL STA.pdf
11. ELECTRICRAFT, INC.
5-18-2022 Daily Report.xls
FBV Morro Bay Joint Venture Page 3 of 6 Printed on 1/24/2023 at 10:58 AM PST
12. Parada Painting Inc.
0518 PARADA STA.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 Yes 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
3 AHERN RENTAL 8.0 Yes 02:10PM
Notes:35' Ariel lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 02:30PM Fastenal 1013 TROD Diffusers
Comments:Created By: Monica Weiss
2 02:30PM FASTENAL 1014 Anchors
Comments:Created By: Monica Weiss
3 02:30PM Ferguson Enterprises, LLC Link Seal
Comments:Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 4 of 6 Printed on 1/24/2023 at 10:58 AM PST
Delivery Log's Attachments:
1.
2022.05.18 Fastenal 1013 T-rod Diffuser.pdf
2.
2022.05.18 Fastenal 1014 Anchors.pdf
3.
2022.05.18 Ferguson Link Seal.pdf
FBV Morro Bay Joint Venture Page 5 of 6 Printed on 1/24/2023 at 10:58 AM PST
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
47°F 58°F 53°F 0.00 in.0.00 in.0.00 in.70%83%98%48°F 4.3 mph 8 mph 12 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
48°F
Clear
52°F
Clear
58°F
Clear
59°F
Clear
58°F
Clear
57°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:50:00 AM No