HomeMy WebLinkAbout2022-05-19FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Thursday 5/19/2022
Daily Log Completed
The Daily Log was completed by Monica Weiss on Thu Jun 2, 2022 at 02:48pmPDT.
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Jobsite clean up
- All roads are being prepped for Granite
- Backfilling PRW and PW lines
- Hills are having the mustard plants mowed down
- Work on the grading for the landscaping continues
- Testing for leaks continues
2 Daniel Ford No 50-RO/UV BUILDING - The Reps for the RO and UV systems are on site.
- Support and install ro/uv system
3 Daniel Ford No 90-CHEMICAL FACILITY - Copper pipe is being run and supported
- Installing the level transmitter
- we are welding and installing chem piping
4 Daniel Ford No 10-SITE OVERALL - Scheduled maintenance is ongoing
5 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- The level sensors for the Cassette tank are being installed
- Pipe supports for the MBR slab are being welded
MANPOWER LOG 17 Workers | 140.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 Dahl Insulation 1 8.0 8.0 70-RESIDUALS
AREA
Notes:Finish metal jacketing on insulated blower piping.
Created By: Eric Girten
2 ELECTRICRAFT, INC.4 8.0 32.0
Notes:Created By: Rick Howland
FBV Morro Bay Joint Venture Page 1 of 6 Printed on 1/24/2023 at 10:58 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
3 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Angel Diaz
Manny Hernandez
Jaren Unfried
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Orlando Cortez
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Laborers
Johnathan Torres
FBV Morro Bay Joint Venture Page 2 of 6 Printed on 1/24/2023 at 10:58 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Daniel Ford
11 0 8.0 0.0
Notes:Apprentice Carpenters
Enrique Padilla
Created By: Daniel Ford
12 Parada Painting Inc.2 10.0 20.0
Notes:Created By: Monica Weiss
17 140.0
Manpower Log's Attachments:
1. Dahl Insulation
0519 DAHL STA.pdf
2. ELECTRICRAFT, INC.
5-19-2022 Daily Report.xls
12. Parada Painting Inc.
0519 PARADA STA.pdf
FBV Morro Bay Joint Venture Page 3 of 6 Printed on 1/24/2023 at 10:58 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 Yes 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
3 AHERN RENTAL 8.0 Yes 02:10PM
Notes:35' Ariel lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 02:35PM Suez Water Technologies &
Solutions
Gaskets Bearings
Comments:Created By: Monica Weiss
2 02:35PM HD Supply White Cap 47273035 Drywall
Comments:Created By: Monica Weiss
3 02:35PM ZORO U-Bolts
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
FBV Morro Bay Joint Venture Page 4 of 6 Printed on 1/24/2023 at 10:58 AM PST
1.
2022.05.19 SUEZ Gaskets Bearings.pdf
2.
2022.05.19 White Cap 47273035 Dryawall.pdf
3.
2022.05.19 ZORO U-bolts No Packing.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
50°F 70°F 56°F 0.00 in.0.00 in.0.00 in.55%79%98%49°F 2.9 mph 4 mph 7 mph
FBV Morro Bay Joint Venture Page 5 of 6 Printed on 1/24/2023 at 10:58 AM PST
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
50°F
Clear
54°F
Clear
56°F
Clear
68°F
Clear
64°F
Clear
56°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 06:20:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 6 of 6 Printed on 1/24/2023 at 10:58 AM PST