Daily Log: Tuesday 5/24/2022
Daily Log Completed
The Daily Log was completed by Monica Weiss on Fri Jun 3, 2022 at 07:04amPDT.
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Jobsite clean up
- All roads are being prepped for Granite
- Backfilling PRW and PW lines
- Work on the grading for the landscaping continues
- Testing for leaks continues
- We are working on the front entrance
2 Daniel Ford No 50-RO/UV BUILDING - The Reps for the RO and UV systems are on site.
- Support and install ro/uv system
3 Daniel Ford No 90-CHEMICAL FACILITY - Copper pipe is being run and supported
- Installing the level transmitter
- we are welding and installing chem piping
- Water lines in chem building
4 Daniel Ford No 10-SITE OVERALL - Scheduled maintenance is ongoing
5 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- The level sensors for the Cassette tank are being installed
- Pipe supports for the MBR slab are being welded
6 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- Cleaning and pressure washing this area
7 Daniel Ford No 20-HEADWORKS AREA - Cleaning and pressure washing this area
FBV Morro Bay Joint Venture Page 1 of 8 Printed on 1/24/2023 at 11:00 AM PST
MANPOWER LOG 16 Workers | 128.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Angel Diaz
Manny Hernandez
Jaren Unfried
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Orlando Cortez
Coy Brite
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 8 Printed on 1/24/2023 at 11:00 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Laborers
Johnathan Torres
Created By: Daniel Ford
9 0 8.0 0.0
Notes:Apprentice Carpenters
Enrique Padilla
Created By: Daniel Ford
10 Dahl Insulation 1 8.0 8.0 30-TREATMENT
AREA
Notes:Blower piping at tank
Created By: Eric Girten
11 ELECTRICRAFT, INC.4 8.0 32.0
Notes:Created By: Rick Howland
16 128.0
Manpower Log's Attachments:
11. ELECTRICRAFT, INC.
5-24-2022 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 Yes 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
3 AHERN RENTAL 8.0 Yes 02:10PM
Notes:35' Ariel lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
FBV Morro Bay Joint Venture Page 3 of 8 Printed on 1/24/2023 at 11:00 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 06:35AM Airgas 5690 Nitrogen
Comments:Created By: Monica Weiss
2 06:35AM Burt Ind 107915 Test Material
Comments:Created By: Monica Weiss
3 06:35AM Ferguson Enterprises, LLC 471-TR511 Test Trees
Comments:Created By: Monica Weiss
4 06:35AM Ferguson Enterprises, LLC Eye Wash Plumbing
Comments:Created By: Monica Weiss
5 06:35AM Ferguson Enterprises, LLC Eye Wash Plumbing
Comments:Created By: Monica Weiss
6 06:35AM Grainger ECI V Belt
Comments:Created By: Monica Weiss
7 06:35AM HARRINGTON INDUSTRIAL
PLASTICS LLC
471-286.1 A90 Sweeps
Comments:Created By: Monica Weiss
8 06:35AM PRW steel 471-318 MBR Supports
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
FBV Morro Bay Joint Venture Page 4 of 8 Printed on 1/24/2023 at 11:00 AM PST
1.
2022.05.24 Airgas 5690 Nitrogen.pdf
2.
2022.05.24 Burt Ind 107915 Test Material.pdf
3.
2022.05.24 Ferguson 471-TR511 Test Tree.pdf
FBV Morro Bay Joint Venture Page 5 of 8 Printed on 1/24/2023 at 11:00 AM PST
4.
2022.05.25 Ferguson Eye Wash .pdf
5.
2022.05.26 Ferguson EyeW Plumbing.pdf
6.
2022.05.26 Grainger ECI V Belt .pdf
FBV Morro Bay Joint Venture Page 6 of 8 Printed on 1/24/2023 at 11:00 AM PST
7.
2022.05.26 Harrington 471-286.1 A90 Sweeps.pdf
8.
2022.05.26 PRW Steel 471-317 .pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
48°F 59°F 54°F 0.00 in.0.00 in.0.00 in.73%83%93%49°F 3.6 mph 6 mph 10 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
49°F
Clear
55°F
Clear
58°F
Clear
60°F
Clear
59°F
Clear
56°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 06:15:00 AM No
FBV Morro Bay Joint Venture Page 7 of 8 Printed on 1/24/2023 at 11:00 AM PST