HomeMy WebLinkAbout2022-05-26FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Thursday 5/26/2022
Daily Log Completed
The Daily Log was completed by Monica Weiss on Fri Jun 3, 2022 at 07:57amPDT.
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Jobsite clean up
- Backfilling PRW and PW lines
- Work on the grading for the landscaping continues
- Testing for leaks continues
- We installing the mail box
2 Daniel Ford No 90-CHEMICAL FACILITY
- Welding and installing chem piping
- Water lines in chem building
3 Daniel Ford No 10-SITE OVERALL - Scheduled maintenance is ongoing
MANPOWER LOG 18 Workers | 148.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 Dahl Insulation 1 8.0 8.0 30-TREATMENT
AREA
Notes:Metal jacket blower piping at tank. Insulate blower piping at cassette tank
Created By: Eric Girten
2 ELECTRICRAFT, INC.4 8.0 32.0
Notes:Created By: Rick Howland
3 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Angel Diaz
Manny Hernandez
Jaren Unfried
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 11:02 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Orlando Cortez
Coy Brite
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Laborers
Johnathan Torres
Created By: Daniel Ford
11 0 8.0 0.0
Notes:Apprentice Carpenters
Enrique Padilla
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 11:02 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
12 Parada Painting Inc.2 10.0 20.0
Notes:Created By: Monica Weiss
18 148.0
Manpower Log's Attachments:
1. Dahl Insulation
0526 DAHL STA.pdf
2. ELECTRICRAFT, INC.
5-26-2022 Daily Report.xls
12. Parada Painting Inc.
0526 PARADA STA.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 Yes 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 11:02 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
2 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
3 AHERN RENTAL 8.0 Yes 02:10PM
Notes:35' Ariel lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 07:20AM Ferguson Enterprises, LLC
Comments:Created By: Monica Weiss
2 07:20AM Ferguson Enterprises, LLC
Comments:Created By: Monica Weiss
3 07:20AM Grainger ECI V belt
Comments:Created By: Monica Weiss
4 07:20AM HARRINGTON INDUSTRIAL
PLASTICS LLC
471-286 A90 Sweeps
Comments:Created By: Monica Weiss
5 07:20AM PRW Steel
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 11:02 AM PST
1.
2022.05.26 Ferguson Eye Wash PLMB.pdf
2.
2022.05.26 Ferguson EyeW Plumbing.pdf
3.
2022.05.26 Grainger ECI V Belt .pdf
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 11:02 AM PST
4.
2022.05.26 Harrington 471-286.1 A90 Sweeps.pdf
5.
2022.05.26 PRW Steel 471-317 .pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
52°F 59°F 55°F 0.01 in.0.01 in.0.01 in.82%94%100%53°F 4.0 mph 7 mph 11 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Partly Cloudy
54°F
Partly Cloudy
55°F
Partly Cloudy
59°F
Partly Cloudy
59°F
Cloudy
54°F
Cloudy
53°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:40:00 AM No