Daily Log: Wednesday 6/1/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Jobsite clean up
- Backfilling PRW and PW lines
- Work on the grading for the landscaping continues
- Testing for leaks continues
- We are cutting the concrete around the edges of the v ditch
for landscapers
- Leak and pipe repair continues for the PW line
2 Daniel Ford No 90-CHEMICAL FACILITY
- Welding and installing chem piping
- Water lines in chem building
3 Daniel Ford No 10-SITE OVERALL Maintenance/Cleaning notes
- As well as the cleaning of buildings and areas
-Swept Water supply storage and pressure washed
-Cleaned trash from RO building
- Swept and cleaned up rocks on asphalt to keep them from
getting ran over.
4 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- Supports at cassette tank were being fabricated and installed
MANPOWER LOG 19 Workers | 152.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 ELECTRICRAFT, INC.6 8.0 48.0
Notes:Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
FBV Morro Bay Joint Venture Page 1 of 5 Printed on 1/24/2023 at 11:03 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Manny Hernandez
Jaren Unfried
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.0 8.0 0.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Laborers
Johnathan Torres
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Carpenters
Enrique Padilla
FBV Morro Bay Joint Venture Page 2 of 5 Printed on 1/24/2023 at 11:03 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Daniel Ford
11 Dahl Insulation 1 8.0 8.0 30-TREATMENT
AREA
Notes:Blower pipe at cassette tank
Created By: Eric Girten
12 ELECTRICRAFT, INC.3 8.0 24.0
Notes:Created By: Rick Howland
19 152.0
Manpower Log's Attachments:
11. Dahl Insulation
0601 DAHL STA.pdf
12. ELECTRICRAFT, INC.
6-1-2022 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 Yes 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 5 Printed on 1/24/2023 at 11:03 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
3 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 12:00PM HARRINGTON INDUSTRIAL
PLASTICS LLC
471-296.1
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.06.01 Harrington 471-296.1.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
50°F 59°F 55°F 0.00 in.0.00 in.0.00 in.68%78%85%48°F 4.5 mph 7 mph 12 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
50°F
Clear
56°F
Clear
59°F
Clear
58°F
Clear
57°F
Clear
54°F
FBV Morro Bay Joint Venture Page 4 of 5 Printed on 1/24/2023 at 11:03 AM PST
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:40:00 AM No