HomeMy WebLinkAbout2022-06-07FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Tuesday 6/7/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Jobsite clean up
- PW lines
- Work on the grading for the landscaping continues
-
2 Daniel Ford No 90-CHEMICAL FACILITY
- Painters are working on this area
- We moved a lot of the scales and skids for the painters to get
in there to do there work today.
3 Daniel Ford No 10-SITE OVERALL Maintenance/Cleaning notes
- We continue to collect floaties and skim out the tops of tanks
- Both entrances were swept and cleared of rocks from the
new entrances.
- The Exterior of the RO and Maintenance building were wiped
down.
- We started wiping down the interior doors and windows in
the ro and maintenance buildings
4 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- We are working on the supports for the bower piping on the
MBR slab
- Supports for the cassette tank were worked on as well
5 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
- Work continues for the added course screen diffusers.
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 11:04 AM PST
MANPOWER LOG 11 Workers | 92.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Jaren Unfried
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.0 8.0 0.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.0 8.0 0.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 11:04 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Laborers
Johnathan Torres
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.0 8.0 0.0
Notes:Apprentice Carpenters
Enrique Padilla
Created By: Daniel Ford
10 ELECTRICRAFT, INC.1 8.0 8.0
Notes:Created By: Rick Howland
11 Dahl Insulation 1 8.0 8.0
Notes:Created By: Monica Weiss
12 Parada Painting Inc.2 10.0 20.0
Notes:Created By: Monica Weiss
11 92.0
Manpower Log's Attachments:
10. ELECTRICRAFT, INC.
6-7-2022 Daily Report.xls
11. Dahl Insulation
0607 DAHL STA.pdf
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 11:04 AM PST
12. Parada Painting Inc.
0607 PARADA STA.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 AHERN RENTAL 8.0 Yes 12:20PM 00-GENERAL
Notes:Back hoe
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
3 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 12:00PM Fastenal Diffusor Anhors
Comments:Created By: Monica Weiss
2 12:00PM Ferguson Enterprises, LLC 471-383 2" YP PVC
Comments:Created By: Monica Weiss
3 12:00PM Grainger 471-322 A90
Comments:Created By: Monica Weiss
4 12:00PM Grainger 471-233 Ball Valve
Comments:Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 11:04 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
5 12:00PM HD Supply White Cap 47478442 Safety
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.06.07 Fastenal Diffuser Anchors.pdf
2.
2022.06.07 Ferguson 2in PVC 471-383 YP.pdf
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 11:04 AM PST
3.
2022.06.07 Grainger 471-322 A90.pdf
4.
2022.06.07 Grainger Ball Valve 471-233.pdf
5.
2022.06.07 White Cap 47478442 Safety.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
50°F 58°F 54°F 0.00 in.0.00 in.0.00 in.77%86%96%50°F 5.7 mph 10 mph 15 mph
FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 11:04 AM PST
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
50°F
Clear
53°F
Clear
56°F
Clear
57°F
Clear
57°F
Clear
56°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:45:00 AM No