No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Jobsite clean up
- Risers at fire hydrants are being installed and backfilled
- The ravine area is being graded
- backfill near the maintenance building
- yard organization is ongoing
2 Daniel Ford No 90-CHEMICAL FACILITY
- Painters are working on this area
- Flowmeters are being worked on for this area.
- Tubing is being run for the chemical lines
3 Daniel Ford No 10-SITE OVERALL Maintenance/Cleaning notes
- site clean up
- cleaning up slabs on the northern side of the projects
- cleaning up rocks at both entrances on the asphalt
4 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- We are working on the supports for the bower piping on the
MBR slab
- Supports for the cassette tank were worked on as well
5 Daniel Ford No 17-OUTDOOR STORAGE
AREA
-Eco blocks were delivered,
-layout was done and Eco blocks were placed in building 17
6 Daniel Ford No 70-RESIDUALS AREA>73-
Residuals Area - SAFE
Filter System
- We are installing an additional hose bib in this area as
directed by the city
7 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
- We are working on some punch list items in that area
8 Daniel Ford No 20-HEADWORKS AREA>21-
Headworks Area -
Headworks
- pads are being grouted as well as other punch list items are
being taken care of
FBV Morro Bay Joint Venture Page 1 of 6 Printed on 1/24/2023 at 11:06 AM PST
NOTES LOG
No.Created By Issue?Location Comments
9 Daniel Ford No 96-MAINTENANCE
BUILDING
- We are cleaning out this building
10 Ernie Peterson No 00-GENERAL
Notes Log's Attachments:
10.
KCI Environmental Inc 6-13-2022 - Rock Mulch - STA FILL.pdf
MANPOWER LOG 14 Workers | 116.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Jaren Unfried
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 6 Printed on 1/24/2023 at 11:06 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.0 8.0 0.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Laborers
Johnathan Torres
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Carpenters
Enrique Padilla
Created By: Daniel Ford
9 Dahl Insulation 1 8.0 8.0 30-TREATMENT
AREA
Notes:Metal jacket compressed air lines
Created By: Eric Girten
10 Parada Painting Inc.2 10.0 20.0
Notes:Created By: Monica Weiss
11 KCI Environmental 3 8.0 24.0 00-GENERAL
Notes:Created By: Ernie Peterson
14 116.0
Manpower Log's Attachments:
FBV Morro Bay Joint Venture Page 3 of 6 Printed on 1/24/2023 at 11:06 AM PST
9. Dahl Insulation
0613 DAHL STA.pdf
10. Parada Painting Inc.
0613 PARADA STA.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 AHERN RENTAL 8.0 Yes 12:20PM 00-GENERAL
Notes:Back hoe
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
3 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 6 Printed on 1/24/2023 at 11:06 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 12:45PM McMaster-CARR Mineral Oil
Comments:Created By: Monica Weiss
2 12:45PM MID-STATE CONCRETE
PRODUCTS, LLC
Eco Blocks
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.06.13 Mcmaster Carr Mineral Oil.pdf
2.
2022.06.13 Midstate Concrete ECO Block.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
53°F 60°F 57°F 0.00 in.0.00 in.0.00 in.69%82%98%51°F 6.8 mph 13 mph 21 mph
FBV Morro Bay Joint Venture Page 5 of 6 Printed on 1/24/2023 at 11:06 AM PST
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
54°F
Clear
57°F
Clear
60°F
Clear
60°F
Clear
59°F
Clear
57°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:50:00 AM No
By Date Copies To