HomeMy WebLinkAbout2022-06-15FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Wednesday 6/15/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Jobsite clean up
- We are cleaning the drain and the level spreader
- yard organization is ongoing
- We are pulling tubing for the chemical system in the vaults
all over the job site
- The grouting continues under pipe supports on the MBR
slab and the sht
- The sample line has been run from the Calcite area to the
IPR area
2 Daniel Ford No 90-CHEMICAL FACILITY
- Painters are working on this area
- Flowmeters are being worked on for this area.
- Tubing is being run for the chemical lines
- All the copper has been connected
3 Daniel Ford No 10-SITE OVERALL Maintenance/Cleaning notes
- site clean up
- cleaning up slabs on the northern side of the projects
- cleaning up rocks at both entrances on the asphalt
- Monthly maintenance is being performed on BNR, MBR,
4 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
- The supports are being grouted
- Temp supports are being moved and the holes patched
back in
5 Ernie Peterson No 00-GENERAL
Notes Log's Attachments:
FBV Morro Bay Joint Venture Page 1 of 6 Printed on 1/24/2023 at 11:06 AM PST
5.
KCI Environmental Inc 6-15-2022 - Rock Mulch - STA FILL.pdf
MANPOWER LOG 12 Workers | 100.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Jaren Unfried
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.0 8.0 0.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 6 Printed on 1/24/2023 at 11:06 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Laborers
Johnathan Torres
Created By: Daniel Ford
8 Dahl Insulation 1 8.0 8.0 90-CHEMICAL
FACILITY
Notes:Insulate/metal jacket hot water copper line
Created By: Eric Girten
9 Parada Painting Inc.2 10.0 20.0
Notes:Created By: Monica Weiss
10 KCI Environmental 2 8.0 16.0 00-GENERAL
Notes:Created By: Ernie Peterson
12 100.0
Manpower Log's Attachments:
8. Dahl Insulation
0615 DAHL STA.pdf
FBV Morro Bay Joint Venture Page 3 of 6 Printed on 1/24/2023 at 11:06 AM PST
9. Parada Painting Inc.
0615 PARADA STA.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 AHERN RENTAL 8.0 Yes 12:20PM 00-GENERAL
Notes:Back hoe
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
3 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 02:00PM Standard Electric Aluminum Rail
Comments:Created By: Monica Weiss
2 02:00PM McMaster-CARR Spill kit for Mercury
Comments:Trojan UV
Created By: Monica Weiss
3 02:00PM Ferguson Enterprises, LLC Final Copper Pieces A90
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
FBV Morro Bay Joint Venture Page 4 of 6 Printed on 1/24/2023 at 11:06 AM PST
1.
2022.06.15 Standard Electric Alum Rail.pdf
2.
2022.06.15 Mcmaster Carr Spill Kit for Mercury.pdf
3.
2022.06.15 Ferguson Copper A90.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
52°F 62°F 56°F 0.00 in.0.00 in.0.00 in.65%78%88%49°F 5.0 mph 8 mph 13 mph
FBV Morro Bay Joint Venture Page 5 of 6 Printed on 1/24/2023 at 11:06 AM PST
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
52°F
Clear
58°F
Clear
60°F
Clear
61°F
Clear
58°F
Clear
56°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:50:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 6 of 6 Printed on 1/24/2023 at 11:06 AM PST