Daily Log: Thursday 6/16/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Jobsite clean up
- We are cleaning the drain and the level spreader
- yard organization is ongoing
- We are pulling tubing for the chemical system in the vaults
all over the job site
- The grouting continues under pipe supports on the MBR slab
and the sht
- The sample line has been run from the Calcite area to the IPR
area
- Scissor lift was picked up today
2 Daniel Ford No 90-CHEMICAL FACILITY
- Painters are working on this area
- Flowmeters are being worked on for this area.
- Tubing is being run for the chemical lines
- All the copper has been connected
3 Daniel Ford No 10-SITE OVERALL Maintenance/Cleaning notes
- site clean up
- cleaning up slabs on the northern side of the projects
- cleaning up rocks at both entrances on the asphalt
- Monthly maintenance is being performed on Safe Filter, RO,
Calcite and a few other misc areas
4 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- We removed blower 2 motor for the Cassette tank at the
direction of the SUEZ rep
5 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
- The supports are being grouted
- Temp supports are being moved and the holes patched back
in
FBV Morro Bay Joint Venture Page 1 of 4 Printed on 1/24/2023 at 11:10 AM PST
MANPOWER LOG 14 Workers | 112.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 ELECTRICRAFT, INC.6 8.0 48.0
Notes:Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Jaren Unfried
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.0 8.0 0.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Laborers
Johnathan Torres
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 4 Printed on 1/24/2023 at 11:10 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
9 Dahl Insulation 1 8.0 8.0 90-CHEMICAL
FACILITY
Notes:Metal jacket insulated hot water copper lines. Material cleanup. Demob from Treatment area
Created By: Eric Girten
14 112.0
Manpower Log's Attachments:
9. Dahl Insulation
0616 DAHL STA.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 AHERN RENTAL 8.0 Yes 12:20PM 00-GENERAL
Notes:Back hoe
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
3 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 4 Printed on 1/24/2023 at 11:10 AM PST
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
51°F 58°F 54°F 0.00 in.0.00 in.0.00 in.78%83%91%50°F 6.6 mph 11 mph 19 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
52°F
Clear
56°F
Clear
58°F
Clear
58°F
Clear
57°F
Clear
53°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 06:20:00 AM No
By Date Copies To