HomeMy WebLinkAbout2022-06-20FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Monday 6/20/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Jobsite clean up
- We are pulling tubing for the chemical system in the vaults
all over the job site
2 Daniel Ford No 90-CHEMICAL FACILITY - We are fixing some of the leaks in the copper
3 Daniel Ford No 10-SITE OVERALL Maintenance/Cleaning notes
- pressure washing the headworks, odor control, fine screens,
and the mbr area.
- performed scheduled maintenance for the Headworks, odor
control, fine screens, BNR, and MBR.
4 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- We removed blower 2 motor for the Cassette tank at the
direction of the SUEZ rep. (extra work ticket created)
- The air lines for the new angle body air valve are being
worked on
5 Monica Weiss No SAFETY TBT SWT
6 Ernie Peterson No 00-GENERAL Begin Irrigation System Installation
Notes Log's Attachments:
5.
06.20 SWT.pdf 06.20 TBT.pdf
FBV Morro Bay Joint Venture Page 1 of 4 Printed on 1/24/2023 at 11:11 AM PST
6.
KCI Environmental Inc 6-20-2022 - Irrigation - STA FILL.pdf
MANPOWER LOG 15 Workers | 120.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 ELECTRICRAFT, INC.6 8.0 48.0
Notes:Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Jaren Unfried
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 4 Printed on 1/24/2023 at 11:11 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
6 J.R. Filanc Construction Company, Inc.0 8.0 0.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
8 KCI Environmental 3 8.0 24.0 00-GENERAL
Notes:Begin Irrigation System Installation
Created By: Ernie Peterson
15 120.0
Manpower Log's Attachments:
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 AHERN RENTAL 8.0 Yes 12:20PM 00-GENERAL
Notes:Back hoe
Created By: Daniel Ford
2 AHERN RENTAL 8.0 Yes 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
3 AHERN RENTAL 8.0 Yes 05:30AM
Notes:Mini Excavator
Created By: Daniel Ford
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
51°F 61°F 56°F 0.00 in.0.00 in.0.00 in.67%78%89%49°F 4.6 mph 8 mph 13 mph
FBV Morro Bay Joint Venture Page 3 of 4 Printed on 1/24/2023 at 11:11 AM PST
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
52°F
Clear
58°F
Clear
59°F
Clear
60°F
Clear
60°F
Clear
57°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 09:35:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 4 of 4 Printed on 1/24/2023 at 11:11 AM PST