HomeMy WebLinkAbout2022-06-21FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Tuesday 6/21/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Jobsite clean up
- We are pulling tubing for the chemical system in the vaults
all over the job site
- Mud is being cleaned out of the v ditch
- We are cleaning all the excess mud out of the level
spreaders.
2 Daniel Ford No 90-CHEMICAL FACILITY - We are fixing some of the leaks in the copper and replacing
a couple defective unions.
3 Daniel Ford No 10-SITE OVERALL Maintenance/Cleaning notes
- We drained the Safe Filter and will clean the entire tank out.
- performed scheduled maintenance for the RO, Calcite,
outfall pumps
4 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- We removed blower 2 motor for the Cassette tank at the
direction of the SUEZ rep. (extra work ticket created)
- The air lines for the new angle body air valve are being
worked on
5 Daniel Ford No 20-HEADWORKS AREA>24-
Headworks Area - Vactor
Washdown
We are working on Punch list items in this area
6 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
Punch list items in this area.
7 Ernie Peterson No 00-GENERAL
Notes Log's Attachments:
FBV Morro Bay Joint Venture Page 1 of 6 Printed on 1/24/2023 at 11:12 AM PST
7.
KCI Environmental Inc 6-21-2022 - Irrigation - STA FILL.pdf
MANPOWER LOG 15 Workers | 120.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 ELECTRICRAFT, INC.6 8.0 48.0
Notes:Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Jaren Unfried
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 6 Printed on 1/24/2023 at 11:12 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
6 J.R. Filanc Construction Company, Inc.0 8.0 0.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
8 KCI Environmental 3 8.0 24.0 00-GENERAL
Notes:Created By: Ernie Peterson
15 120.0
Manpower Log's Attachments:
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 AHERN RENTAL 8.0 No 12:20PM 00-GENERAL
Notes:Back hoe
Created By: Daniel Ford
2 shoretech No 07:55AM
Notes:Trench Box
Created By: Daniel Ford
3 shoretech No 07:55AM
Notes:street plate
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 02:00PM Suez Water Technologies &
Solutions
CSI Check Valve, Sight Glass, Gauge
Comments:Compressor
Created By: Monica Weiss
2 02:00PM McMaster-CARR SS Tubing
Comments:Suez Air Fittings
FBV Morro Bay Joint Venture Page 3 of 6 Printed on 1/24/2023 at 11:12 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
Created By: Monica Weiss
3 02:00PM SAFETRITE DAVITS for RELOCATION
Comments:Created By: Monica Weiss
4 02:00PM SEC Standard Electric Relay Contact
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.06.20 CSI Compressor SCI SUEZ Check Valve Glass Gauge.pdf
2.
2022.06.20 McMaster Carr SS Tubing.pdf
FBV Morro Bay Joint Venture Page 4 of 6 Printed on 1/24/2023 at 11:12 AM PST
3.
2022.06.20 Safetrite 3M Davits.pdf
4.
2022.06.20 Standard Electric Relay Contact.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
55°F 79°F 65°F 0.00 in.0.00 in.0.00 in.36%60%85%51°F 4.0 mph 7 mph 10 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
68°F
Clear
79°F
Clear
69°F
Clear
70°F
Clear
62°F
Clear
64°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:50:00 AM No
FBV Morro Bay Joint Venture Page 5 of 6 Printed on 1/24/2023 at 11:12 AM PST
By Date Copies To
FBV Morro Bay Joint Venture Page 6 of 6 Printed on 1/24/2023 at 11:12 AM PST