Daily Log: Friday 6/24/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Jobsite clean up
- We are pulling tubing for the chemical system in the vaults
all over the job site.
-Chemical lines are being tied in.
- Mud is being cleaned out of the v ditch drain
- We are cleaning all the excess mud out of the level
spreaders.
- backfilling by the dewatering slab
2 Daniel Ford No 90-CHEMICAL FACILITY - All leaks are fixed and we are up and running in this area.
3 Daniel Ford No 10-SITE OVERALL Maintenance/Cleaning notes
- We ran the entire system today (water loops)
- checked all eyewash stations in the chem area showers
4 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- Punch list items are being worked on in this area.
- Troy spent almost all day working on the air compressors
and air lines for the suez rep.
5 Daniel Ford No 20-HEADWORKS AREA>24-
Headworks Area - Vactor
Washdown
We are working on Punch list items in this area
6 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
Punch list items in this area.
7 Ernie Peterson No 00-GENERAL
Notes Log's Attachments:
FBV Morro Bay Joint Venture Page 1 of 4 Printed on 1/24/2023 at 11:13 AM PST
7.
KCI Environmental Inc 6-24-2022 - Irrigation - STA FILL.pdf
MANPOWER LOG 15 Workers | 120.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 Dahl Insulation 1 8.0 8.0 90-CHEMICAL
FACILITY
Notes:Insulate/metal jacket hot water copper
Created By: Eric Girten
2 ELECTRICRAFT, INC.6 8.0 48.0
Notes:Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Jaren Unfried
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 4 Printed on 1/24/2023 at 11:13 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.0 8.0 0.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.0 8.0 0.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
9 KCI Environmental 3 8.0 24.0 00-GENERAL
Notes:Created By: Ernie Peterson
15 120.0
Manpower Log's Attachments:
1. Dahl Insulation
0624 DAHL STA.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 AHERN RENTAL 8.0 No 12:20PM 00-GENERAL
Notes:Back hoe
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 4 Printed on 1/24/2023 at 11:13 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
2 shoretech No 07:55AM
Notes:Trench Box
Created By: Daniel Ford
3 shoretech No 07:55AM
Notes:street plate
Created By: Daniel Ford
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
51°F 64°F 56°F 0.00 in.0.00 in.0.00 in.77%93%100%53°F 2.7 mph 5 mph 5 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Fog
51°F
Cloudy
58°F
Clear
64°F
Partly Cloudy
63°F
Cloudy
58°F
Fog
55°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 07:55:00 AM No