HomeMy WebLinkAbout2022-07-12FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Tuesday 7/12/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Jobsite clean up
- The trench drains at pond 1 and 2 are being worked on
- the 24 inch declor pipe replacement pieces arrived and we
glued them all together
- Valves for the dewatering were removed
2 Daniel Ford No 10-SITE OVERALL Maintenance/Cleaning notes
- Scheduled maintenance was performed on equipment
- deep clean of the Safe filter and water exchange
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- Punch list items
4 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
- Punch list items
5 Daniel Ford No 60-PRODUCT WATER AREA - We are installing the supports for the IPR pumps in this area
6 Ernie Peterson No 00-GENERAL
Notes Log's Attachments:
6.
KCI Environmental Inc 7-12-2022 - Irrigation - STA FILL.pdf KCI daily - 7-12-2022.pdf
FBV Morro Bay Joint Venture Page 1 of 6 Printed on 1/24/2023 at 12:25 PM PST
KCI Environmental Inc 7-12-2022 - Rock Mulch - STA FILL.pdf KCI daily - 7-12-2022.pdf
MANPOWER LOG 10 Workers | 80.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Jaren Unfried
Daniel Waddle
Manny Hernandez
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.0 8.0 0.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 6 Printed on 1/24/2023 at 12:25 PM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Laborers
Jonathan Torres
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Operators
Trevor Hernandez
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Apprentice
Micah Pixley
Created By: Monica Weiss
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Journeyman
Rick Jenne
Created By: Monica Weiss
10 80.0
Manpower Log's Attachments:
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 AHERN RENTAL 8.0 No 12:20PM 00-GENERAL
Notes:Back hoe
Created By: Daniel Ford
2 shoretech No 07:55AM
Notes:Trench Box
Created By: Daniel Ford
3 shoretech No 07:55AM
Notes:8 street plates
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 6 Printed on 1/24/2023 at 12:25 PM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 03:35PM HD Supply White Cap Set 3G epoxy
Comments:Created By: Monica Weiss
2 03:35PM HARRINGTON INDUSTRIAL
PLASTICS LLC
24in PVC 90
Comments:Created By: Monica Weiss
3 03:35PM Miner's Ace Hardware 74286 dwatering
Comments:Created By: Monica Weiss
4 03:35PM Miner's Ace Hardware 742781 charter Dewatering
Comments:Created By: Monica Weiss
5 03:35PM Miner's Ace Hardware 742804 charter Dewatering
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.07.12 White Cap SET3G 48031238.pdf
FBV Morro Bay Joint Venture Page 4 of 6 Printed on 1/24/2023 at 12:25 PM PST
2.
2022.07.12 Harrington 24in PVC 90.pdf
3.
2022.07.12 Miners 74286 Dewatering.pdf
4.
2022.07.12 Miners 742781 Charter Dewatering.pdf
FBV Morro Bay Joint Venture Page 5 of 6 Printed on 1/24/2023 at 12:25 PM PST
5.
2022.07.12 Miners 742804 Charter Dewatering.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
53°F 62°F 58°F 0.00 in.0.00 in.0.00 in.83%93%100%56°F 2.7 mph 4 mph 6 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Fog
54°F
Cloudy
60°F
Cloudy
61°F
Cloudy
63°F
Cloudy
61°F
Fog
60°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:45:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 6 of 6 Printed on 1/24/2023 at 12:25 PM PST