HomeMy WebLinkAbout2022-07-13FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Wednesday 7/13/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Jobsite clean up
- The trench drains at pond 1 and 2 are being formed
- The 24" Decleor pipe is being fabricated today
- Access for the conveyor truck is being made today
- Property line on the eastern side has been shot in
2 Daniel Ford No 10-SITE OVERALL Maintenance/Cleaning notes
- Scheduled maintenance was performed on equipment
- deep clean of the Safe filter and water exchange
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- Punch list items
4 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
- Punch list items
5 Daniel Ford No 60-PRODUCT WATER AREA - Punch list items
6 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
- Punch list items
MANPOWER LOG 11 Workers | 88.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Jaren Unfried
Daniel Waddle
Manny Hernandez
FBV Morro Bay Joint Venture Page 1 of 4 Printed on 1/24/2023 at 12:25 PM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice Laborers
Jonathan Torres
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Operators
Trevor Hernandez
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Apprentice
Micah Pixley
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Journeyman
Rick Jenne
Created By: Daniel Ford
11 88.0
FBV Morro Bay Joint Venture Page 2 of 4 Printed on 1/24/2023 at 12:25 PM PST
Manpower Log's Attachments:
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 AHERN RENTAL 8.0 No 12:20PM 00-GENERAL
Notes:Back hoe
Created By: Daniel Ford
2 shoretech No 07:55AM
Notes:Trench Box
Created By: Daniel Ford
3 shoretech No 07:55AM
Notes:8 street plates
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 03:35PM Suez Water Technologies &
Solutions
Electric Motor E&L
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.07.13 Suez Electric Motor E&L.pdf
FBV Morro Bay Joint Venture Page 3 of 4 Printed on 1/24/2023 at 12:25 PM PST
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
54°F 65°F 57°F 0.00 in.0.00 in.0.00 in.73%91%100%55°F 4.5 mph 8 mph 12 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Partly Cloudy
56°F
Partly Cloudy
58°F
Clear
65°F
Clear
61°F
Partly Cloudy
60°F
Partly Cloudy
56°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 02:10:00 PM No