HomeMy WebLinkAbout2022-07-22FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Friday 7/22/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - General clean up
- Yard area was organized
2 Daniel Ford No 10-SITE OVERALL Maintenance/Cleaning notes
- Scheduled maintenance was performed on equipment
- Chlorine readings were taken at three locations
- We are draining/cleaning the SHT tank and cleaning the
dewatering area
- We ran both water loops today at 3MGD all day (1.5 MGD
each way)
3 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
- Punch list items
4 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- Punch list items
5 Daniel Ford No 50-RO/UV BUILDING - Punch list items
MANPOWER LOG 6 Workers | 48.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Jaren Unfried
Manny Hernandez
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 1 of 3 Printed on 1/24/2023 at 12:28 PM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.0 8.0 0.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Operators
Trevor Hernandez
Created By: Daniel Ford
6 48.0
Manpower Log's Attachments:
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 AHERN RENTAL 8.0 No 12:20PM 00-GENERAL
Notes:Back hoe
Created By: Daniel Ford
2 shoretech No 07:55AM
Notes:Trench Box
Created By: Daniel Ford
3 shoretech No 07:55AM
Notes:8 street plates
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 3 Printed on 1/24/2023 at 12:28 PM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 03:35PM McMaster-CARR CPVC Pipe
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.07.22 Mcmaster Carr CPVC Pipe.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
52°F 60°F 55°F 0.00 in.0.00 in.0.00 in.77%88%99%52°F 4.8 mph 8 mph 12 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Partly Cloudy
52°F
Partly Cloudy
54°F
Clear
59°F
Clear
58°F
Clear
60°F
Clear
57°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 06:15:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 3 of 3 Printed on 1/24/2023 at 12:28 PM PST