HomeMy WebLinkAbout2022-08-01FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Monday 8/1/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Rock placement, drainage, and work on the front entrance is
being preformed
- Punch list items
2 Daniel Ford No 10-SITE OVERALL Maintenance/Cleaning notes
- Chlorine was tested today and the level was at 0.24 water
loops were run today at 3MGD all day (1.5 MGD each way)
- Weekly preventative maintenance was performed on the
odor control (A alarm is lit for the fan and its not running)
headworks, and the fine screens.
3 Daniel Ford No 50-RO/UV BUILDING - Fabricated and installed the 6" PVC flush line and support
- the holes in the overhead pipe supports were all drilled today
and we have begun to install the cross supports
4 Daniel Ford No 30-TREATMENT AREA - Plastic was put on the edges of the sun screens for the flow
control boxes on the catwalk
- Punch list items
5 Daniel Ford No 96-MAINTENANCE
BUILDING - Punch list items
6 Daniel Ford No 95-OPERATIONS
BUILDING
- the leak in the conference room was taken care of today
- more drywall was removed today to be in compliance with
the mold report from green home solutions. they are
scheduled to be back on site on Thursday 8/4 for a final
inspection
- Josh from Miltimore tile was contacted
FBV Morro Bay Joint Venture Page 1 of 6 Printed on 1/24/2023 at 12:35 PM PST
MANPOWER LOG 6 Workers | 48.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Elija Pauls
Daniel Waddle
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Pipe fitter
Rick Dayton
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.0 8.0 0.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Operators
Trevor Hernandez
Created By: Daniel Ford
6 48.0
Manpower Log's Attachments:
FBV Morro Bay Joint Venture Page 2 of 6 Printed on 1/24/2023 at 12:35 PM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 AHERN RENTAL 8.0 No 12:20PM 00-GENERAL
Notes:Back hoe
Created By: Daniel Ford
2 shoretech No 07:55AM
Notes:Trench Box
Created By: Daniel Ford
3 shoretech No 07:55AM
Notes:8 street plates
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 01:25PM Miners 744447 Dewatering
Comments:Created By: Monica Weiss
2 01:25PM USA Blue Book colorimeter Samples
Comments:Created By: Monica Weiss
3 01:25PM McMaster-CARR Punchlist
Comments:Created By: Monica Weiss
4 01:25PM McMaster-CARR Punchlist 2
Comments:Created By: Monica Weiss
5 01:25PM JB DEWAR, INC
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
FBV Morro Bay Joint Venture Page 3 of 6 Printed on 1/24/2023 at 12:35 PM PST
1.
2022.08.01Miners 744447 Deawtering.pdf
2.
2022.08.01 USA Bluebook colorimeter sample.pdf
3.
2022.08.01 Mcmaster Carr Punchlist.pdf
FBV Morro Bay Joint Venture Page 4 of 6 Printed on 1/24/2023 at 12:35 PM PST
4.
2022.08.01 Mcmaster Carr Punchlist (2).pdf
5.
2022.08.01 JB Dewar 214511.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
59°F 67°F 63°F 0.00 in.0.01 in.0.01 in.76%84%95%58°F 3.2 mph 7 mph 10 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Partly Cloudy
61°F
Clear
65°F
Clear
66°F
Partly Cloudy
67°F
Partly Cloudy
67°F
Partly Cloudy
61°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 06:30:00 AM No
FBV Morro Bay Joint Venture Page 5 of 6 Printed on 1/24/2023 at 12:35 PM PST
By Date Copies To
FBV Morro Bay Joint Venture Page 6 of 6 Printed on 1/24/2023 at 12:35 PM PST