Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Monday 8/15/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - working on the connexs,laydown yard, shipping materia off
site and organizing is ongoing
- Punch list items all over the job site
2 Daniel Ford No 10-SITE OVERALL Maintenance/Cleaning notes
- cleaning and adding a ARV on the WWR line
- chlorine is at 0.78 in the BNR tank this morning
3 Daniel Ford No 70-RESIDUALS AREA>73-
Residuals Area - SAFE Filter
System
- Punch list items
4 Daniel Ford No 90-CHEMICAL FACILITY - Punch list items were worked on
5 Daniel Ford No 50-RO/UV BUILDING - Punch list Items were worked on
MANPOWER LOG 6 Workers | 48.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Elija Pauls
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:General Foreman
Daniel Ford
FBV Morro Bay Joint Venture Page 1 of 4 Printed on 1/24/2023 at 12:42 PM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Operators
Trevor Hernandez
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Cement Mason
Danie Sheslingoff
Created By: Daniel Ford
6 48.0
Manpower Log's Attachments:
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 AHERN RENTAL 8.0 No 12:20PM 00-GENERAL
Notes:Back hoe
Created By: Daniel Ford
2 shoretech No 07:55AM
Notes:Trench Box
Created By: Daniel Ford
3 shoretech No 07:55AM
Notes:8 street plates
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 01:25PM Grainger ARV Coupling
Comments:Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 2 of 4 Printed on 1/24/2023 at 12:42 PM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
2 01:25PM CAPITAL FLOW INC A20 Pipe & Fittings
Comments:Created By: Monica Weiss
3 01:25PM CAPITAL FLOW INC A20 Flanges & Elbows
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.08.15 Grainger ARV Coupling.pdf
2.
2022.08.15 Capflo A20 Pipe and Fittings.pdf
FBV Morro Bay Joint Venture Page 3 of 4 Printed on 1/24/2023 at 12:42 PM PST
3.
2022.08.15 Capflo A20 Flange Elbows.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
52°F 57°F 55°F 0.00 in.0.00 in.0.00 in.71%87%97%51°F 4.1 mph 6 mph 10 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
55°F
Clear
54°F
Clear
57°F
Clear
58°F
Clear
56°F
Clear
55°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 06:45:00 AM No